Luxur Tower By Imtiaz construction progress
The registered completion date for Luxur Tower By Imtiaz in Jumeirah Village Circle is December 2026. At the last site inspection, in September 2026, it was 90% built. The developer is Imtiaz Real Estate Investment & Development.
90%
Built, at the site inspection of 17 September 2026
On pace for its date
- Registered completion date
- December 2026
- Finish at recent pace
- December 2026
- Construction started
- July 2023
- First registered
- October 2023
- Community
- Jumeirah Village Circle
- Units
- 361
- Escrow bank
- United Bank Limited
- Name in Arabic
- برج لكسورمن امتياز
- Project number
- 2770
- Site inspections
- 9
Schedule
Since October 2025 Luxur Tower By Imtiaz has added about 3.5 points a month. That puts 100% around December 2026, within three months of its registered completion date of December 2026.
Site inspections
17 September 2026
90%+10.0 pts
4 June 2026
80%+16 pts
26 February 2026
64%+14 pts
6 October 2025
50%+22 pts
4 June 2025
28%+11 pts
13 January 2025
17%+8.3 pts
17 September 2024
8.9%+7.3 pts
14 March 2024
1.6%+1.6 pts
7 September 2023
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Luxur Tower By Imtiaz?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Luxur Tower By Imtiaz handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Luxur Tower By Imtiaz?
- Luxur Tower By Imtiaz was 90% built at the site inspection on 17 September 2026. The site has been inspected 9 times since September 2023. The Land Department took 62 site photos at its inspections.
- Is Luxur Tower By Imtiaz delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
- Who is building Luxur Tower By Imtiaz?
- The registered developer is Imtiaz Real Estate Investment & Development. It has 10 other projects under construction in Dubai.
- Which bank holds the escrow account for Luxur Tower By Imtiaz?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cove Living Residence By ImtiazAlso by Imtiaz Real Estate Investment & Development. 63%, Due April 2027.
- Cove Edition Residence 1 By ImtiazAlso by Imtiaz Real Estate Investment & Development. 90%, Due August 2026, passed.
- Cove Edition Residence 2 By ImtiazAlso by Imtiaz Real Estate Investment & Development. 60%, Due October 2026, passed.
- Cove Edition Residence 3 By ImtiazAlso by Imtiaz Real Estate Investment & Development. 44%, Due December 2026.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)