Skip to content

Cove Edition Residence 1 By Imtiaz construction progress

Cove Edition Residence 1 By Imtiaz in Dubai Land Residence Complex was registered to complete in August 2026 and is still under construction. At the last site inspection, in October 2026, it was 90% built. The developer is Imtiaz Real Estate Investment & Development.

90%

Built, at the site inspection of 12 October 2026

3 months past its registered completion date

Registered completion date
August 2026
Finish at recent pace
December 2026
Construction started
August 2024
First registered
September 2024
Units
182
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كوف ايديشن ريزيدنس 1 من امتياز
Project number
3248
Site inspections
7

Schedule

Cove Edition Residence 1 By Imtiaz was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 5.5 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 October 2026

90%+24 pts

  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 1, 12 October 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 2, 12 October 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 3, 12 October 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 4, 12 October 2026

13 July 2026

66%+17 pts

  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 1, 13 July 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 2, 13 July 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 3, 13 July 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 4, 13 July 2026

9 April 2026

50%+12 pts

  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 1, 9 April 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 2, 9 April 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 3, 9 April 2026
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 4, 9 April 2026

29 December 2025

38%+17 pts

  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 1, 29 December 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 2, 29 December 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 3, 29 December 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 4, 29 December 2025

9 September 2025

21%+8.8 pts

  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 1, 9 September 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 2, 9 September 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 3, 9 September 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 4, 9 September 2025

14 May 2025

12%+12 pts

  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 1, 14 May 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 2, 14 May 2025
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 3, 14 May 2025

9 September 2024

0%

  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 1, 9 September 2024
  • Cove Edition Residence 1 By Imtiaz construction site, inspection photo 2, 9 September 2024

All 49 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Cove Edition Residence 1 By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cove Edition Residence 1 By Imtiaz handover date?
The registered completion date was August 2026, and the register still lists Cove Edition Residence 1 By Imtiaz as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cove Edition Residence 1 By Imtiaz?
Cove Edition Residence 1 By Imtiaz was 90% built at the site inspection on 12 October 2026. The site has been inspected 7 times since September 2024. The Land Department took 49 site photos at its inspections.
Is Cove Edition Residence 1 By Imtiaz delayed?
Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
Who is building Cove Edition Residence 1 By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Cove Edition Residence 1 By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.