Cove Edition Residence 4 By Imtiaz construction progress

The registered completion date for Cove Edition Residence 4 By Imtiaz in Dubai Land Residence Complex is January 2027. At the last site inspection, in November 2026, it was 40% built. The developer is Imtiaz Real Estate Investment & Development.

40%

Built, at the site inspection of 6 November 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
September 2028
Construction started
January 2025
First registered
January 2025
Units
260
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كوف إيديشن ريزيدنس 4 من امتياز
Project number
3483
Site inspections
7

Schedule

Between January 2026 and November 2026 the site added about 2.7 points a month. At that rate it would finish around September 2028, more than three months after its registered date of January 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 November 2026

40%+9.8 pts

  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 1, 6 November 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 2, 6 November 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 3, 6 November 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 4, 6 November 2026

4 August 2026

30%+9.7 pts

  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 1, 4 August 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 2, 4 August 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 3, 4 August 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 4, 4 August 2026

4 May 2026

21%+5.4 pts

  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 1, 4 May 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 2, 4 May 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 3, 4 May 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 4, 4 May 2026

27 January 2026

15%+9.8 pts

  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 1, 27 January 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 2, 27 January 2026
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 3, 27 January 2026

8 October 2025

5.2%+4.2 pts

  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 1, 8 October 2025
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 2, 8 October 2025
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 3, 8 October 2025

4 June 2025

1.0%+1.0 pts

  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 1, 4 June 2025
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 2, 4 June 2025
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 3, 4 June 2025
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 4, 4 June 2025

13 January 2025

0%

  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 1, 13 January 2025
  • Cove Edition Residence 4 By Imtiaz construction site, inspection photo 2, 13 January 2025

All 45 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Cove Edition Residence 4 By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cove Edition Residence 4 By Imtiaz handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cove Edition Residence 4 By Imtiaz?
Cove Edition Residence 4 By Imtiaz was 40% built at the site inspection on 6 November 2026. The site has been inspected 7 times since January 2025. The Land Department took 45 site photos at its inspections.
Is Cove Edition Residence 4 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Cove Edition Residence 4 By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Cove Edition Residence 4 By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.