Cove Edition Residence 4 By Imtiaz construction photos

45 photos from 7 site inspections, newest first. The percentage is how much of Cove Edition Residence 4 By Imtiaz was built on the day of each visit.

6 November 202640% built

4 August 202630% built

4 May 202621% built

27 January 202615% built

8 October 20255.2% built

4 June 20251.0% built

13 January 20250% built

Back to Cove Edition Residence 4 By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.