Cove Edition Residence 3 By Imtiaz construction progress

The registered completion date for Cove Edition Residence 3 By Imtiaz in Dubai Land Residence Complex is December 2026. At the last site inspection, in October 2026, it was 44% built. The developer is Imtiaz Real Estate Investment & Development.

44%

Built, at the site inspection of 26 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
July 2028
Construction started
December 2024
First registered
January 2025
Units
260
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كوف إيديشن ريزيدنس 3 من امتياز
Project number
3466
Site inspections
8

Schedule

Between January 2026 and October 2026 the site added about 2.7 points a month. At that rate it would finish around July 2028, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 October 2026

44%+6.9 pts

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 26 October 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 26 October 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 3, 26 October 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 4, 26 October 2026

20 July 2026

37%+13 pts

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 20 July 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 20 July 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 3, 20 July 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 4, 20 July 2026

21 April 2026

24%+5.3 pts

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 21 April 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 21 April 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 3, 21 April 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 4, 21 April 2026

13 January 2026

18%+9.7 pts

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 13 January 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 13 January 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 3, 13 January 2026
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 4, 13 January 2026

8 October 2025

8.8%+5.8 pts

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 8 October 2025
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 8 October 2025
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 3, 8 October 2025

25 July 2025

3.0%+2.5 pts

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 25 July 2025
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 25 July 2025
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 3, 25 July 2025
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 4, 25 July 2025

23 April 2025

0.4%+0.4 pts

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 23 April 2025
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 23 April 2025
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 3, 23 April 2025

25 December 2024

0%

  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 1, 25 December 2024
  • Cove Edition Residence 3 By Imtiaz construction site, inspection photo 2, 25 December 2024

All 41 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Cove Edition Residence 3 By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cove Edition Residence 3 By Imtiaz handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cove Edition Residence 3 By Imtiaz?
Cove Edition Residence 3 By Imtiaz was 44% built at the site inspection on 26 October 2026. The site has been inspected 8 times since December 2024. The Land Department took 41 site photos at its inspections.
Is Cove Edition Residence 3 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Cove Edition Residence 3 By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Cove Edition Residence 3 By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.