Cove Edition Residence 3 By Imtiaz construction progress
The registered completion date for Cove Edition Residence 3 By Imtiaz in Dubai Land Residence Complex is December 2026. At the last site inspection, in October 2026, it was 44% built. The developer is Imtiaz Real Estate Investment & Development.
44%
Built, at the site inspection of 26 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- July 2028
- Construction started
- December 2024
- First registered
- January 2025
- Community
- Dubai Land Residence Complex
- Units
- 260
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- كوف إيديشن ريزيدنس 3 من امتياز
- Project number
- 3466
- Site inspections
- 8
Schedule
Between January 2026 and October 2026 the site added about 2.7 points a month. At that rate it would finish around July 2028, more than three months after its registered date of December 2026.
Site inspections
26 October 2026
44%+6.9 pts
20 July 2026
37%+13 pts
21 April 2026
24%+5.3 pts
13 January 2026
18%+9.7 pts
8 October 2025
8.8%+5.8 pts
25 July 2025
3.0%+2.5 pts
23 April 2025
0.4%+0.4 pts
25 December 2024
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Cove Edition Residence 3 By Imtiaz?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Cove Edition Residence 3 By Imtiaz handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Cove Edition Residence 3 By Imtiaz?
- Cove Edition Residence 3 By Imtiaz was 44% built at the site inspection on 26 October 2026. The site has been inspected 8 times since December 2024. The Land Department took 41 site photos at its inspections.
- Is Cove Edition Residence 3 By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Cove Edition Residence 3 By Imtiaz?
- The registered developer is Imtiaz Real Estate Investment & Development. It has 10 other projects under construction in Dubai.
- Which bank holds the escrow account for Cove Edition Residence 3 By Imtiaz?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luxur Tower By ImtiazAlso by Imtiaz Real Estate Investment & Development. 90%, Due December 2026.
- Cove Living Residence By ImtiazAlso by Imtiaz Real Estate Investment & Development. 63%, Due April 2027.
- Cove Edition Residence 1 By ImtiazAlso by Imtiaz Real Estate Investment & Development. 90%, Due August 2026, passed.
- Cove Edition Residence 2 By ImtiazAlso by Imtiaz Real Estate Investment & Development. 60%, Due October 2026, passed.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)