Cove Edition Residence 3 By Imtiaz construction photos

41 photos from 8 site inspections, newest first. The percentage is how much of Cove Edition Residence 3 By Imtiaz was built on the day of each visit.

26 October 202644% built

20 July 202637% built

21 April 202624% built

13 January 202618% built

8 October 20258.8% built

25 July 20253.0% built

23 April 20250.4% built

25 December 20240% built

Back to Cove Edition Residence 3 By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.