Cove Edition Residence 1 By Imtiaz construction photos

49 photos from 7 site inspections, newest first. The percentage is how much of Cove Edition Residence 1 By Imtiaz was built on the day of each visit.

12 October 202690% built

13 July 202666% built

9 April 202650% built

29 December 202538% built

9 September 202521% built

14 May 202512% built

9 September 20240% built

Back to Cove Edition Residence 1 By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.