Cove Boulevard By Imtiaz construction progress

Cove Boulevard By Imtiaz in Dubai Land Residence Complex is 10% built at the Land Department inspection of September 2026. Developer Imtiaz Real Estate Investment & Development. Completion registered for October 2028.

10%

Built, at the Land Department site inspection of 30 September 2026

Running behind its date

Completion date (Land Department)
October 2028
Finish at recent pace
June 2035
Construction started
May 2025
Registered with the Land Department
May 2025
Units
436
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كوف بوليفارد من امتياز
Land Department project number
3675
Land Department site inspections
7

Schedule

Between October 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around June 2035, more than three months after the October 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 September 2026

10%+4.5 pts

  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 1, 30 September 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 2, 30 September 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 3, 30 September 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 4, 30 September 2026

27 April 2026

5.9%+1.6 pts

  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 1, 27 April 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 2, 27 April 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 3, 27 April 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 4, 27 April 2026

27 January 2026

4.3%+3.2 pts

  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 1, 27 January 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 2, 27 January 2026
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 3, 27 January 2026

24 October 2025

1.1%+0.5 pts

  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 1, 24 October 2025
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 2, 24 October 2025

13 October 2025

0.6%+0.4 pts

  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 1, 13 October 2025
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 2, 13 October 2025

30 June 2025

0.1%+0.1 pts

  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 1, 30 June 2025
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 2, 30 June 2025
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 3, 30 June 2025
  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 4, 30 June 2025

10 April 2025

0%

  • Cove Boulevard By Imtiaz construction site, Land Department inspection photo 1, 10 April 2025

All 21 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Cove Boulevard By Imtiaz is behind that average.

Imtiaz Real Estate Investment & Development has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Cove Boulevard By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Cove Boulevard By Imtiaz be completed?
The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around June 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Cove Boulevard By Imtiaz is built?
10%, measured at the Land Department site inspection on 30 September 2026. The Land Department engineers have inspected the site 7 times since April 2025.
Is Cove Boulevard By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Cove Boulevard By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Cove Boulevard By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.