21 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Cove Boulevard By Imtiaz was built on the day of each visit.

30 September 202610% built

27 April 20265.9% built

27 January 20264.3% built

24 October 20251.1% built

13 October 20250.6% built

30 June 20250.1% built

10 April 20250% built

Back to Cove Boulevard By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.