Skip to content

Blue Wave construction progress

The register lists Blue Wave in Dubai Land Residence Complex as complete, with a registered completion date of January 2023. Its last site inspection on record was in January 2023. The developer is Tiger Properties.

100%

Built, at the site inspection of 30 January 2023

Construction complete

Registered completion date
January 2023
Construction started
November 2019
First registered
October 2019
Units
578
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بلو ويف
Project number
2165
Site inspections
6

Schedule

The register lists Blue Wave as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 January 2023

100%+3.0 pts

  • Blue Wave construction site, inspection photo 1, 30 January 2023
  • Blue Wave construction site, inspection photo 2, 30 January 2023
  • Blue Wave construction site, inspection photo 3, 30 January 2023
  • Blue Wave construction site, inspection photo 4, 30 January 2023

9 January 2023

97%+41 pts

  • Blue Wave construction site, inspection photo 1, 9 January 2023
  • Blue Wave construction site, inspection photo 2, 9 January 2023
  • Blue Wave construction site, inspection photo 3, 9 January 2023
  • Blue Wave construction site, inspection photo 4, 9 January 2023

7 April 2022

56%+25 pts

  • Blue Wave construction site, inspection photo 1, 7 April 2022
  • Blue Wave construction site, inspection photo 2, 7 April 2022
  • Blue Wave construction site, inspection photo 3, 7 April 2022
  • Blue Wave construction site, inspection photo 4, 7 April 2022

6 September 2021

31%+9.1 pts

  • Blue Wave construction site, inspection photo 1, 6 September 2021
  • Blue Wave construction site, inspection photo 2, 6 September 2021
  • Blue Wave construction site, inspection photo 3, 6 September 2021
  • Blue Wave construction site, inspection photo 4, 6 September 2021

15 March 2021

22%+17 pts

  • Blue Wave construction site, inspection photo 1, 15 March 2021
  • Blue Wave construction site, inspection photo 2, 15 March 2021
  • Blue Wave construction site, inspection photo 3, 15 March 2021
  • Blue Wave construction site, inspection photo 4, 15 March 2021

22 June 2020

5.3%

  • Blue Wave construction site, inspection photo 1, 22 June 2020
  • Blue Wave construction site, inspection photo 2, 22 June 2020
  • Blue Wave construction site, inspection photo 3, 22 June 2020
  • Blue Wave construction site, inspection photo 4, 22 June 2020

All 68 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Blue Wave?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Blue Wave handover date?
Construction of Blue Wave is recorded as complete, with a registered completion date of January 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Blue Wave?
Blue Wave was 100% built at the site inspection on 30 January 2023. The site has been inspected 6 times since June 2020. The Land Department took 68 site photos at its inspections.
Is Blue Wave delayed?
The register lists construction as complete.
Who is building Blue Wave?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Blue Wave?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.