Ag 9ine construction progress

No completion date is registered for Ag 9ine in Dubai Land Residence Complex yet. At the last site inspection, in July 2026, it was 38% built. The developer is Ag Properties.

38%

Built, at the site inspection of 30 July 2026

Finish at recent pace
May 2029
Construction started
January 2024
First registered
February 2024
Developer
Ag Properties
Units
260
Escrow bank
Emirates NBD
Name in Arabic
ايه جي 9 ناين
Project number
2847
Site inspections
4

Schedule

Since February 2026 Ag 9ine has added about 1.8 points a month. At that rate the site reaches 100% around May 2029. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

30 July 2026

38%+10 pts

  • Ag 9ine construction site, inspection photo 1, 30 July 2026
  • Ag 9ine construction site, inspection photo 2, 30 July 2026
  • Ag 9ine construction site, inspection photo 3, 30 July 2026
  • Ag 9ine construction site, inspection photo 4, 30 July 2026

12 February 2026

28%+14 pts

  • Ag 9ine construction site, inspection photo 1, 12 February 2026
  • Ag 9ine construction site, inspection photo 2, 12 February 2026
  • Ag 9ine construction site, inspection photo 3, 12 February 2026
  • Ag 9ine construction site, inspection photo 4, 12 February 2026

21 March 2025

15%+15 pts

  • Ag 9ine construction site, inspection photo 1, 21 March 2025
  • Ag 9ine construction site, inspection photo 2, 21 March 2025
  • Ag 9ine construction site, inspection photo 3, 21 March 2025
  • Ag 9ine construction site, inspection photo 4, 21 March 2025

11 January 2024

0%

  • Ag 9ine construction site, inspection photo 1, 11 January 2024
  • Ag 9ine construction site, inspection photo 2, 11 January 2024
  • Ag 9ine construction site, inspection photo 3, 11 January 2024

All 27 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Ag Properties has 4 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Ag 9ine?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ag 9ine handover date?
No completion date is on record for Ag 9ine yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Ag 9ine?
Ag 9ine was 38% built at the site inspection on 30 July 2026. The site has been inspected 4 times since January 2024. The Land Department took 27 site photos at its inspections.
Who is building Ag 9ine?
The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Ag 9ine?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.