Ag 9ine construction progress
No completion date is registered for Ag 9ine in Dubai Land Residence Complex yet. At the last site inspection, in July 2026, it was 38% built. The developer is Ag Properties.
38%
Built, at the site inspection of 30 July 2026
- Finish at recent pace
- May 2029
- Construction started
- January 2024
- First registered
- February 2024
- Developer
- Ag Properties
- Community
- Dubai Land Residence Complex
- Units
- 260
- Escrow bank
- Emirates NBD
- Name in Arabic
- ايه جي 9 ناين
- Project number
- 2847
- Site inspections
- 4
Schedule
Since February 2026 Ag 9ine has added about 1.8 points a month. At that rate the site reaches 100% around May 2029. No completion date is on record to compare it with.
Site inspections
30 July 2026
38%+10 pts
12 February 2026
28%+14 pts
21 March 2025
15%+15 pts
11 January 2024
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Ag Properties has 4 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Ag 9ine?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ag 9ine handover date?
- No completion date is on record for Ag 9ine yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Ag 9ine?
- Ag 9ine was 38% built at the site inspection on 30 July 2026. The site has been inspected 4 times since January 2024. The Land Department took 27 site photos at its inspections.
- Who is building Ag 9ine?
- The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Ag 9ine?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ag CentralAlso by Ag Properties. 59%, Due October 2026, passed.
- Ag SquareAlso by Ag Properties. 69%, Due September 2026, passed.
- Ag 7evenAlso by Ag Properties. 94%, Due March 2027.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Samana Ivy GardensNearby in Dubai Land Residence Complex. 41%.
- A 99Nearby in Dubai Land Residence Complex. 48%, Due October 2026, passed.
- Samana Park MeadowsNearby in Dubai Land Residence Complex. 38%, Due August 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)