Ag Central construction photos
39 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Ag Central was built on the day of each visit.
17 September 202659% built
9 February 202651% built
13 October 202548% built
21 March 202538% built
16 October 202424% built
18 September 20232.3% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.