Off-plan projects in Dubai Investment Park Second
27 projects in Dubai Investment Park Second are under construction. On average they are 12% built. The next one due is Damac Riverside - Lush, in December 2027.
- Damac Riverside - LushDamac Mry Investment42%Due December 2027
- Damac Riverside - IvyDamac Mry Investment38%Due December 2027
- Damac Riverside Views - Marine 4Damac Mry Investment21%Due May 2028
- Grand Polo - Selvara 2Emaar Development20%Due April 2029
- Damac Riverside Views - Marine 3Damac Mry Investment18%Due May 2028
- Damac Riverside Views - Royal 1Damac Mry Investment14%Due March 2029
- Damac Riverside Views - Royal 2Damac Mry Investment14%Due March 2029
- Damac Riverside Views - Royal 3&4Damac Mry Investment13%Due March 2029
- Damac Riverside - SageDamac Mry Investment13%Due December 2027
- Grand Polo - SelvaraEmaar Development12%Due April 2029
- Damac Riverside Views - Indigo 1Damac Mry Investment12%Due March 2029
- Damac Riverside Views - Marine 2Damac Mry Investment12%Due May 2028
- Damac Riverside Views - Indigo 2Damac Mry Investment12%Due March 2029
- Damac Riverside Views - Marine 1Damac Mry Investment12%Due May 2028
- Grand Polo - MonturaEmaar Development11%Due June 2029
- Grand Polo - Chevalia FieldsEmaar Development10%Due April 2029
- Damac Riverside Views - Capri 2Damac Mry Investment8.3%Due March 2029
- Damac Riverside Views - Capri 1Damac Mry Investment8.2%Due March 2029
- Damac Riverside Views - Azure 2Damac Mry Investment5.8%Due March 2029
- Damac Riverside - OliveDamac Mry Investment5.5%Due June 2028
- Damac Riverside Views - Azure 1Damac Mry Investment5.5%Due March 2029
- Grand Polo - Montura 2Emaar Development5.0%Due May 2029
- Grand Polo - Chevalia Estate 2Emaar Development4.1%Due June 2029
- Grand Polo - Selvara 3Emaar Development3.0%Due May 2029
- Grand Polo - Selvara 4Emaar Development2.9%Due May 2029
- Grand Polo - Chevalia EstateEmaar Development2.3%Due February 2029
- Grand Polo - Montura 3Emaar Development1.1%Due June 2029
Questions
How many off-plan projects are under construction in Dubai Investment Park Second?
27 projects are under construction in Dubai Investment Park Second, 12% built on average at the latest site inspections.
Which Dubai Investment Park Second projects are due to finish next?
By registered completion date: Damac Riverside - Lush (December 2027, 42% built), Damac Riverside - Ivy (December 2027, 38% built) and Damac Riverside - Sage (December 2027, 13% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Dubai Investment Park Second projects are past their completion date?
None. Every project here with a registered completion date is still inside it.
Which developers are building in Dubai Investment Park Second?
The developers with the most projects here are Damac Mry Investment (17) and Emaar Development (10), out of 2 building in Dubai Investment Park Second.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.