Damac Riverside - Lush construction progress

The registered completion date for Damac Riverside - Lush in Dubai Investment Park Second is December 2027. At the last site inspection, in August 2026, it was 42% built. The developer is Damac Mry Investment.

42%

Built, at the site inspection of 26 August 2026

On pace for its date

Registered completion date
December 2027
Finish at recent pace
February 2028
Construction started
September 2024
First registered
July 2024
Units
744
Escrow bank
Emirates NBD
Name in Arabic
داماك ريفرسايد - لاش
Project number
3169
Site inspections
6

Schedule

Since November 2025 Damac Riverside - Lush has added about 3.3 points a month. That puts 100% around February 2028, within three months of its registered completion date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 August 2026

42%+16 pts

  • Damac Riverside - Lush construction site, inspection photo 1, 26 August 2026
  • Damac Riverside - Lush construction site, inspection photo 2, 26 August 2026
  • Damac Riverside - Lush construction site, inspection photo 3, 26 August 2026
  • Damac Riverside - Lush construction site, inspection photo 4, 26 August 2026

14 April 2026

26%+15 pts

  • Damac Riverside - Lush construction site, inspection photo 1, 14 April 2026
  • Damac Riverside - Lush construction site, inspection photo 2, 14 April 2026
  • Damac Riverside - Lush construction site, inspection photo 3, 14 April 2026
  • Damac Riverside - Lush construction site, inspection photo 4, 14 April 2026

18 November 2025

11%+7.8 pts

  • Damac Riverside - Lush construction site, inspection photo 1, 18 November 2025
  • Damac Riverside - Lush construction site, inspection photo 2, 18 November 2025
  • Damac Riverside - Lush construction site, inspection photo 3, 18 November 2025
  • Damac Riverside - Lush construction site, inspection photo 4, 18 November 2025

15 July 2025

3.5%+2.8 pts

  • Damac Riverside - Lush construction site, inspection photo 1, 15 July 2025
  • Damac Riverside - Lush construction site, inspection photo 2, 15 July 2025
  • Damac Riverside - Lush construction site, inspection photo 3, 15 July 2025
  • Damac Riverside - Lush construction site, inspection photo 4, 15 July 2025

25 February 2025

0.7%+0.7 pts

  • Damac Riverside - Lush construction site, inspection photo 1, 25 February 2025
  • Damac Riverside - Lush construction site, inspection photo 2, 25 February 2025
  • Damac Riverside - Lush construction site, inspection photo 3, 25 February 2025

1 July 2024

0%

  • Damac Riverside - Lush construction site, inspection photo 1, 1 July 2024
  • Damac Riverside - Lush construction site, inspection photo 2, 1 July 2024

All 33 site photos, by inspection date

Context

Dubai Investment Park Second has 27 projects under construction, 12% built on average.

Damac Mry Investment has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Damac Riverside - Lush?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Riverside - Lush handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Riverside - Lush?
Damac Riverside - Lush was 42% built at the site inspection on 26 August 2026. The site has been inspected 6 times since July 2024. The Land Department took 33 site photos at its inspections.
Is Damac Riverside - Lush delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
Who is building Damac Riverside - Lush?
The registered developer is Damac Mry Investment. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Riverside - Lush?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.