Grand Polo - Chevalia Fields construction progress

The registered completion date for Grand Polo - Chevalia Fields in Dubai Investment Park Second is April 2029. At the last site inspection, in July 2026, it was 10% built. The developer is Emaar Development.

10%

Built, at the site inspection of 21 July 2026

Running behind its date

Registered completion date
April 2029
Finish at recent pace
February 2033
Construction started
March 2025
First registered
April 2025
Units
179
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
جراند بولو - شيفاليا فيلدز
Project number
3701
Site inspections
4

Schedule

Between November 2025 and July 2026 the site added about 1.1 points a month. At that rate it would finish around February 2033, more than three months after its registered date of April 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 July 2026

10%+8.7 pts

  • Grand Polo - Chevalia Fields construction site, inspection photo 1, 21 July 2026
  • Grand Polo - Chevalia Fields construction site, inspection photo 2, 21 July 2026
  • Grand Polo - Chevalia Fields construction site, inspection photo 3, 21 July 2026
  • Grand Polo - Chevalia Fields construction site, inspection photo 4, 21 July 2026

4 March 2026

1.4%+1.0 pts

  • Grand Polo - Chevalia Fields construction site, inspection photo 1, 4 March 2026
  • Grand Polo - Chevalia Fields construction site, inspection photo 2, 4 March 2026
  • Grand Polo - Chevalia Fields construction site, inspection photo 3, 4 March 2026
  • Grand Polo - Chevalia Fields construction site, inspection photo 4, 4 March 2026

4 November 2025

0.3%+0.3 pts

  • Grand Polo - Chevalia Fields construction site, inspection photo 1, 4 November 2025
  • Grand Polo - Chevalia Fields construction site, inspection photo 2, 4 November 2025
  • Grand Polo - Chevalia Fields construction site, inspection photo 3, 4 November 2025
  • Grand Polo - Chevalia Fields construction site, inspection photo 4, 4 November 2025

18 April 2025

0%

  • Grand Polo - Chevalia Fields construction site, inspection photo 1, 18 April 2025

All 18 site photos, by inspection date

Context

Dubai Investment Park Second has 27 projects under construction, 12% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Grand Polo - Chevalia Fields?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Grand Polo - Chevalia Fields handover date?
The registered completion date is April 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Grand Polo - Chevalia Fields?
Grand Polo - Chevalia Fields was 10% built at the site inspection on 21 July 2026. The site has been inspected 4 times since April 2025. The Land Department took 18 site photos at its inspections.
Is Grand Polo - Chevalia Fields delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2029.
Who is building Grand Polo - Chevalia Fields?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Grand Polo - Chevalia Fields?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.