Grand Polo - Chevalia Fields construction progress

Grand Polo - Chevalia Fields in Dubai Investment Park Second is 10% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for April 2029.

10%

Built, at the Land Department site inspection of 21 July 2026

Running behind its date

Completion date (Land Department)
April 2029
Finish at recent pace
February 2033
Construction started
March 2025
Registered with the Land Department
April 2025
Units
179
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
جراند بولو - شيفاليا فيلدز
Land Department project number
3701
Land Department site inspections
4

Schedule

Between November 2025 and July 2026 the site added about 1.1 points a month. At that rate it would finish around February 2033, more than three months after the April 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 July 2026

10%+8.7 pts

  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 1, 21 July 2026
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 2, 21 July 2026
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 3, 21 July 2026
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 4, 21 July 2026

4 March 2026

1.4%+1.0 pts

  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 1, 4 March 2026
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 2, 4 March 2026
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 3, 4 March 2026
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 4, 4 March 2026

4 November 2025

0.3%+0.3 pts

  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 1, 4 November 2025
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 2, 4 November 2025
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 3, 4 November 2025
  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 4, 4 November 2025

18 April 2025

0%

  • Grand Polo - Chevalia Fields construction site, Land Department inspection photo 1, 18 April 2025

All 18 site photos, by inspection date

Context

Dubai Investment Park Second has 27 projects under construction, 11% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Grand Polo - Chevalia Fields?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Grand Polo - Chevalia Fields be completed?
The completion date registered with the Dubai Land Department is April 2029. At the pace of its recent inspections the site would reach 100% around February 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Grand Polo - Chevalia Fields is built?
10%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 4 times since April 2025.
Is Grand Polo - Chevalia Fields delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2029.
Who is building Grand Polo - Chevalia Fields?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Grand Polo - Chevalia Fields?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.