Grand Polo - Selvara construction progress

The registered completion date for Grand Polo - Selvara in Dubai Investment Park Second is April 2029. At the last site inspection, in May 2026, it was 2.8% built. The developer is Emaar Development.

12%

Built, at the site inspection of 14 May 2026

Running behind its date

Registered completion date
April 2029
Finish at recent pace
June 2058
Construction started
November 2025
First registered
June 2025
Units
237
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
جراند بولو - سيلفارا
Project number
3822
Site inspections
3

Schedule

Between June 2025 and May 2026 the site added about 0.3 points a month. At that rate it would finish around June 2058, more than three months after its registered date of April 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2026

2.8%+2.2 pts

  • Grand Polo - Selvara construction site, inspection photo 1, 14 May 2026
  • Grand Polo - Selvara construction site, inspection photo 2, 14 May 2026
  • Grand Polo - Selvara construction site, inspection photo 3, 14 May 2026
  • Grand Polo - Selvara construction site, inspection photo 4, 14 May 2026

5 January 2026

0.7%+0.7 pts

  • Grand Polo - Selvara construction site, inspection photo 1, 5 January 2026
  • Grand Polo - Selvara construction site, inspection photo 2, 5 January 2026
  • Grand Polo - Selvara construction site, inspection photo 3, 5 January 2026
  • Grand Polo - Selvara construction site, inspection photo 4, 5 January 2026

9 June 2025

0%

  • Grand Polo - Selvara construction site, inspection photo 1, 9 June 2025
  • Grand Polo - Selvara construction site, inspection photo 2, 9 June 2025

All 12 site photos, by inspection date

Context

Dubai Investment Park Second has 27 projects under construction, 12% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Grand Polo - Selvara?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Grand Polo - Selvara handover date?
The registered completion date is April 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2058. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Grand Polo - Selvara?
Grand Polo - Selvara was 12% built at the site inspection on 14 May 2026. The site has been inspected 3 times since June 2025. The Land Department took 12 site photos at its inspections.
Is Grand Polo - Selvara delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2029.
Who is building Grand Polo - Selvara?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Grand Polo - Selvara?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.