Grand Polo - Chevalia Estate 2 construction progress

The registered completion date for Grand Polo - Chevalia Estate 2 in Dubai Investment Park Second is June 2029. At the last site inspection, in June 2026, it was 4.1% built. The developer is Emaar Development.

4.1%

Built, at the site inspection of 25 June 2026

Running behind its date

Registered completion date
June 2029
Finish at recent pace
October 2045
Construction started
February 2026
First registered
September 2025
Units
124
Escrow bank
Dubai Islamic Bank
Name in Arabic
جراند بولو - شيفاليا استيت 2
Project number
4067
Site inspections
3

Schedule

Between August 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around October 2045, more than three months after its registered date of June 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 June 2026

4.1%+3.5 pts

  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 1, 25 June 2026
  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 2, 25 June 2026
  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 3, 25 June 2026
  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 4, 25 June 2026

11 March 2026

0.6%+0.6 pts

  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 1, 11 March 2026
  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 2, 11 March 2026
  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 3, 11 March 2026

28 August 2025

0%

  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 1, 28 August 2025
  • Grand Polo - Chevalia Estate 2 construction site, inspection photo 2, 28 August 2025

All 11 site photos, by inspection date

Context

Dubai Investment Park Second has 27 projects under construction, 12% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Grand Polo - Chevalia Estate 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Grand Polo - Chevalia Estate 2 handover date?
The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2045. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Grand Polo - Chevalia Estate 2?
Grand Polo - Chevalia Estate 2 was 4.1% built at the site inspection on 25 June 2026. The site has been inspected 3 times since August 2025. The Land Department took 11 site photos at its inspections.
Is Grand Polo - Chevalia Estate 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Grand Polo - Chevalia Estate 2?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Grand Polo - Chevalia Estate 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.