Grand Polo - Chevalia Estate 2 construction progress
Grand Polo - Chevalia Estate 2 in Dubai Investment Park Second is 4.1% built at the Land Department inspection of June 2026. Developer Emaar Development. Completion registered for June 2029.
4.1%
Built, at the Land Department site inspection of 25 June 2026
Running behind its date
- Completion date (Land Department)
- June 2029
- Finish at recent pace
- October 2045
- Construction started
- February 2026
- Registered with the Land Department
- September 2025
- Developer
- Emaar Development
- Community
- Dubai Investment Park Second
- Units
- 124
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- جراند بولو - شيفاليا استيت 2
- Land Department project number
- 4067
- Land Department site inspections
- 3
Schedule
Between August 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around October 2045, more than three months after the June 2029 date registered with the Land Department.
Site inspections
25 June 2026
4.1%+3.5 pts
11 March 2026
0.6%+0.6 pts
28 August 2025
0%
Context
Dubai Investment Park Second has 27 projects under construction, 11% built on average. Grand Polo - Chevalia Estate 2 is behind that average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Grand Polo - Chevalia Estate 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Grand Polo - Chevalia Estate 2 be completed?
- The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around October 2045. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Grand Polo - Chevalia Estate 2 is built?
- 4.1%, measured at the Land Department site inspection on 25 June 2026. The Land Department engineers have inspected the site 3 times since August 2025.
- Is Grand Polo - Chevalia Estate 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Grand Polo - Chevalia Estate 2?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Grand Polo - Chevalia Estate 2?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Damac Riverside - LushNearby in Dubai Investment Park Second. 42%.
- Damac Riverside - IvyNearby in Dubai Investment Park Second. 38%.
- Damac Riverside - SageNearby in Dubai Investment Park Second. 13%, Due December 2027.
- Damac Riverside Views - Marine 1Nearby in Dubai Investment Park Second. 12%, Due May 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)