Grand Polo - Chevalia Estate 2 construction progress
The registered completion date for Grand Polo - Chevalia Estate 2 in Dubai Investment Park Second is June 2029. At the last site inspection, in June 2026, it was 4.1% built. The developer is Emaar Development.
4.1%
Built, at the site inspection of 25 June 2026
Running behind its date
- Registered completion date
- June 2029
- Finish at recent pace
- October 2045
- Construction started
- February 2026
- First registered
- September 2025
- Developer
- Emaar Development
- Community
- Dubai Investment Park Second
- Units
- 124
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- جراند بولو - شيفاليا استيت 2
- Project number
- 4067
- Site inspections
- 3
Schedule
Between August 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around October 2045, more than three months after its registered date of June 2029.
Site inspections
25 June 2026
4.1%+3.5 pts
11 March 2026
0.6%+0.6 pts
28 August 2025
0%
Context
Dubai Investment Park Second has 27 projects under construction, 12% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Grand Polo - Chevalia Estate 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Grand Polo - Chevalia Estate 2 handover date?
- The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2045. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Grand Polo - Chevalia Estate 2?
- Grand Polo - Chevalia Estate 2 was 4.1% built at the site inspection on 25 June 2026. The site has been inspected 3 times since August 2025. The Land Department took 11 site photos at its inspections.
- Is Grand Polo - Chevalia Estate 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Grand Polo - Chevalia Estate 2?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Grand Polo - Chevalia Estate 2?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Damac Riverside - LushNearby in Dubai Investment Park Second. 42%, Due December 2027.
- Damac Riverside - IvyNearby in Dubai Investment Park Second. 38%, Due December 2027.
- Damac Riverside - SageNearby in Dubai Investment Park Second. 13%, Due December 2027.
- Damac Riverside Views - Marine 1Nearby in Dubai Investment Park Second. 12%, Due May 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)