Damac Riverside Views - Marine 2 construction progress

The registered completion date for Damac Riverside Views - Marine 2 in Dubai Investment Park Second is May 2028. At the last site inspection, in July 2026, it was 12% built. The developer is Damac Mry Investment.

12%

Built, at the site inspection of 16 July 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
October 2032
Construction started
January 2025
First registered
November 2024
Units
358
Escrow bank
First Abu Dhabi Bank
Name in Arabic
داماك ريفرسايد فيوز - مارين 2
Project number
3373
Site inspections
4

Schedule

Between February 2026 and July 2026 the site added about 1.2 points a month. At that rate it would finish around October 2032, more than three months after its registered date of May 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 July 2026

12%+6.0 pts

  • Damac Riverside Views - Marine 2 construction site, inspection photo 1, 16 July 2026
  • Damac Riverside Views - Marine 2 construction site, inspection photo 2, 16 July 2026
  • Damac Riverside Views - Marine 2 construction site, inspection photo 3, 16 July 2026
  • Damac Riverside Views - Marine 2 construction site, inspection photo 4, 16 July 2026

11 February 2026

6.0%+5.8 pts

  • Damac Riverside Views - Marine 2 construction site, inspection photo 1, 11 February 2026
  • Damac Riverside Views - Marine 2 construction site, inspection photo 2, 11 February 2026
  • Damac Riverside Views - Marine 2 construction site, inspection photo 3, 11 February 2026
  • Damac Riverside Views - Marine 2 construction site, inspection photo 4, 11 February 2026

20 May 2025

0.2%+0.2 pts

  • Damac Riverside Views - Marine 2 construction site, inspection photo 1, 20 May 2025
  • Damac Riverside Views - Marine 2 construction site, inspection photo 2, 20 May 2025
  • Damac Riverside Views - Marine 2 construction site, inspection photo 3, 20 May 2025
  • Damac Riverside Views - Marine 2 construction site, inspection photo 4, 20 May 2025

31 October 2024

0%

  • Damac Riverside Views - Marine 2 construction site, inspection photo 1, 31 October 2024
  • Damac Riverside Views - Marine 2 construction site, inspection photo 2, 31 October 2024

All 16 site photos, by inspection date

Context

Dubai Investment Park Second has 27 projects under construction, 12% built on average.

Damac Mry Investment has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Damac Riverside Views - Marine 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Riverside Views - Marine 2 handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Riverside Views - Marine 2?
Damac Riverside Views - Marine 2 was 12% built at the site inspection on 16 July 2026. The site has been inspected 4 times since October 2024. The Land Department took 16 site photos at its inspections.
Is Damac Riverside Views - Marine 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Damac Riverside Views - Marine 2?
The registered developer is Damac Mry Investment. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Riverside Views - Marine 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.