Damac Riverside Views - Marine 4 construction progress

Damac Riverside Views - Marine 4 in Dubai Investment Park Second is 21% built at the Land Department inspection of August 2026. Developer Damac Mry Investment. Completion registered for May 2028.

21%

Built, at the Land Department site inspection of 26 August 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
January 2031
Construction started
January 2025
Registered with the Land Department
November 2024
Units
276
Escrow bank
First Abu Dhabi Bank
Name in Arabic
داماك ريفرسايد فيوز - مارين 4
Land Department project number
3375
Land Department site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 1.5 points a month. At that rate it would finish around January 2031, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

26 August 2026

21%+12 pts

  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 1, 26 August 2026
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 2, 26 August 2026
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 3, 26 August 2026
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 4, 26 August 2026

10 April 2026

9.2%+2.2 pts

  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 1, 10 April 2026
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 2, 10 April 2026
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 3, 10 April 2026
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 4, 10 April 2026

11 November 2025

7.0%+6.8 pts

  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 1, 11 November 2025
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 2, 11 November 2025
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 3, 11 November 2025
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 4, 11 November 2025

20 May 2025

0.2%+0.2 pts

  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 1, 20 May 2025
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 2, 20 May 2025
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 3, 20 May 2025
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 4, 20 May 2025

31 October 2024

0%

  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 1, 31 October 2024
  • Damac Riverside Views - Marine 4 construction site, Land Department inspection photo 2, 31 October 2024

All 26 site photos, by inspection date

Context

Dubai Investment Park Second has 27 projects under construction, 11% built on average.

Damac Mry Investment has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Damac Riverside Views - Marine 4?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac Riverside Views - Marine 4 be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around January 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Riverside Views - Marine 4 is built?
21%, measured at the Land Department site inspection on 26 August 2026. The Land Department engineers have inspected the site 5 times since October 2024.
Is Damac Riverside Views - Marine 4 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Damac Riverside Views - Marine 4?
The registered developer is Damac Mry Investment. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Riverside Views - Marine 4?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.