330 Riverside Crescent construction progress
330 Riverside Crescent in Bukadra is 60% built at the Land Department inspection of July 2026. Developer Sobha.
60%
Built, at the Land Department site inspection of 9 July 2026
Schedule
Since July 2025 330 Riverside Crescent has added about 2.6 points a month. At that rate the site reaches 100% around October 2027. The Land Department has no completion date on record to compare it with.
Site inspections
9 July 2026
60%+11 pts
18 March 2026
49%+11 pts
10 November 2025
38%+6.8 pts
28 July 2025
31%+7.6 pts
16 April 2025
23%+3.3 pts
7 January 2025
20%+4.3 pts
17 September 2024
16%+8.0 pts
23 May 2024
7.7%+7.7 pts
12 October 2023
0%
Context
Bukadra has 21 projects under construction, 26% built on average. 330 Riverside Crescent is ahead of that average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in 330 Riverside Crescent?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will 330 Riverside Crescent be completed?
- The Land Department has no completion date on record for 330 Riverside Crescent yet. It appears once the developer registers the construction timeline.
- How much of 330 Riverside Crescent is built?
- 60%, measured at the Land Department site inspection on 9 July 2026. The Land Department engineers have inspected the site 9 times since October 2023.
- Who is building 330 Riverside Crescent?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for 330 Riverside Crescent?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 37%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vistas HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- Claydon House By EllingtonNearby in Bukadra. 16%, Due December 2027.
- The Waterway By Prestige OneNearby in Bukadra. 15%, Due June 2027.
- Parkway By Prestige OneNearby in Bukadra. 11%, Due January 2028.
- Ayaan Heights INearby in Bukadra. 20%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.