330 Riverside Crescent construction progress
No completion date is registered for 330 Riverside Crescent in Bukadra yet. At the last site inspection, in October 2026, it was 68% built. The developer is Sobha.
68%
Built, at the site inspection of 12 October 2026
Schedule
Since November 2025 330 Riverside Crescent has added about 2.7 points a month. At that rate the site reaches 100% around October 2027. No completion date is on record to compare it with.
Site inspections
12 October 2026
68%+7.4 pts
9 July 2026
60%+11 pts
18 March 2026
49%+11 pts
10 November 2025
38%+6.8 pts
28 July 2025
31%+7.6 pts
16 April 2025
23%+3.3 pts
7 January 2025
20%+4.3 pts
17 September 2024
16%+8.0 pts
23 May 2024
7.7%+7.7 pts
12 October 2023
0%
Context
Bukadra has 21 projects under construction, 27% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in 330 Riverside Crescent?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 330 Riverside Crescent handover date?
- No completion date is on record for 330 Riverside Crescent yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on 330 Riverside Crescent?
- 330 Riverside Crescent was 68% built at the site inspection on 12 October 2026. The site has been inspected 10 times since October 2023. The Land Department took 65 site photos at its inspections.
- Who is building 330 Riverside Crescent?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for 330 Riverside Crescent?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- Claydon House By EllingtonNearby in Bukadra. 16%, Due December 2027.
- The Waterway By Prestige OneNearby in Bukadra. 15%, Due June 2027.
- Parkway By Prestige OneNearby in Bukadra. 11%, Due January 2028.
- Ayaan Heights INearby in Bukadra. 20%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)











.jpg&w=3840&q=75)
.jpg&w=3840&q=75)