330 Riverside Crescent construction progress

No completion date is registered for 330 Riverside Crescent in Bukadra yet. At the last site inspection, in October 2026, it was 68% built. The developer is Sobha.

68%

Built, at the site inspection of 12 October 2026

Finish at recent pace
October 2027
Construction started
October 2023
First registered
January 2024
Developer
Sobha
Community
Bukadra
Units
767
Escrow bank
Emirates Islamic Bank
Name in Arabic
ريفرسايد كريسنت 330
Project number
2788
Site inspections
10

Schedule

Since November 2025 330 Riverside Crescent has added about 2.7 points a month. At that rate the site reaches 100% around October 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

12 October 2026

68%+7.4 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 12 October 2026
  • 330 Riverside Crescent construction site, inspection photo 2, 12 October 2026
  • 330 Riverside Crescent construction site, inspection photo 3, 12 October 2026
  • 330 Riverside Crescent construction site, inspection photo 4, 12 October 2026

9 July 2026

60%+11 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 9 July 2026
  • 330 Riverside Crescent construction site, inspection photo 2, 9 July 2026
  • 330 Riverside Crescent construction site, inspection photo 3, 9 July 2026
  • 330 Riverside Crescent construction site, inspection photo 4, 9 July 2026

18 March 2026

49%+11 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 18 March 2026
  • 330 Riverside Crescent construction site, inspection photo 2, 18 March 2026
  • 330 Riverside Crescent construction site, inspection photo 3, 18 March 2026
  • 330 Riverside Crescent construction site, inspection photo 4, 18 March 2026

10 November 2025

38%+6.8 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 10 November 2025
  • 330 Riverside Crescent construction site, inspection photo 2, 10 November 2025
  • 330 Riverside Crescent construction site, inspection photo 3, 10 November 2025
  • 330 Riverside Crescent construction site, inspection photo 4, 10 November 2025

28 July 2025

31%+7.6 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 28 July 2025
  • 330 Riverside Crescent construction site, inspection photo 2, 28 July 2025
  • 330 Riverside Crescent construction site, inspection photo 3, 28 July 2025
  • 330 Riverside Crescent construction site, inspection photo 4, 28 July 2025

16 April 2025

23%+3.3 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 16 April 2025
  • 330 Riverside Crescent construction site, inspection photo 2, 16 April 2025
  • 330 Riverside Crescent construction site, inspection photo 3, 16 April 2025
  • 330 Riverside Crescent construction site, inspection photo 4, 16 April 2025

7 January 2025

20%+4.3 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 7 January 2025
  • 330 Riverside Crescent construction site, inspection photo 2, 7 January 2025
  • 330 Riverside Crescent construction site, inspection photo 3, 7 January 2025
  • 330 Riverside Crescent construction site, inspection photo 4, 7 January 2025

17 September 2024

16%+8.0 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 17 September 2024
  • 330 Riverside Crescent construction site, inspection photo 2, 17 September 2024
  • 330 Riverside Crescent construction site, inspection photo 3, 17 September 2024
  • 330 Riverside Crescent construction site, inspection photo 4, 17 September 2024

23 May 2024

7.7%+7.7 pts

  • 330 Riverside Crescent construction site, inspection photo 1, 23 May 2024
  • 330 Riverside Crescent construction site, inspection photo 2, 23 May 2024
  • 330 Riverside Crescent construction site, inspection photo 3, 23 May 2024
  • 330 Riverside Crescent construction site, inspection photo 4, 23 May 2024

12 October 2023

0%

  • 330 Riverside Crescent construction site, inspection photo 1, 12 October 2023
  • 330 Riverside Crescent construction site, inspection photo 2, 12 October 2023

All 65 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 27% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 330 Riverside Crescent?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 330 Riverside Crescent handover date?
No completion date is on record for 330 Riverside Crescent yet. Handover follows completion, so there is no date to give.
What is the latest construction update on 330 Riverside Crescent?
330 Riverside Crescent was 68% built at the site inspection on 12 October 2026. The site has been inspected 10 times since October 2023. The Land Department took 65 site photos at its inspections.
Who is building 330 Riverside Crescent?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for 330 Riverside Crescent?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.