Sobha Seahaven Tower A construction photos
44 photos from 7 site inspections, newest first. The percentage is how much of Sobha Seahaven Tower A was built on the day of each visit.
9 November 202645% built
6 August 202637% built
27 April 202631% built
15 January 202627% built
12 September 202522% built
17 October 202411% built
9 February 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.