Beach Vista construction progress

The register lists Beach Vista in Dubai Harbour as complete, with a registered completion date of January 2022. Its last site inspection on record was in December 2021. The developer is Emaar Development.

100%

Built, at the site inspection of 26 December 2021

Construction complete

Registered completion date
January 2022
Construction started
March 2018
First registered
January 2018
Community
Dubai Harbour
Units
466
Escrow bank
Emirates NBD
Name in Arabic
بيتش فيستا
Project number
2015
Site inspections
13

Schedule

The register lists Beach Vista as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 December 2021

100%+1.7 pts

  • Beach Vista construction site, inspection photo 1, 26 December 2021
  • Beach Vista construction site, inspection photo 2, 26 December 2021
  • Beach Vista construction site, inspection photo 3, 26 December 2021
  • Beach Vista construction site, inspection photo 4, 26 December 2021

10 November 2021

98%+4.2 pts

  • Beach Vista construction site, inspection photo 1, 10 November 2021
  • Beach Vista construction site, inspection photo 2, 10 November 2021
  • Beach Vista construction site, inspection photo 3, 10 November 2021
  • Beach Vista construction site, inspection photo 4, 10 November 2021

28 July 2021

94%+6.1 pts

  • Beach Vista construction site, inspection photo 1, 28 July 2021
  • Beach Vista construction site, inspection photo 2, 28 July 2021
  • Beach Vista construction site, inspection photo 3, 28 July 2021
  • Beach Vista construction site, inspection photo 4, 28 July 2021

6 April 2021

88%+14 pts

  • Beach Vista construction site, inspection photo 1, 6 April 2021
  • Beach Vista construction site, inspection photo 2, 6 April 2021
  • Beach Vista construction site, inspection photo 3, 6 April 2021
  • Beach Vista construction site, inspection photo 4, 6 April 2021

16 December 2020

74%+11 pts

  • Beach Vista construction site, inspection photo 1, 16 December 2020
  • Beach Vista construction site, inspection photo 2, 16 December 2020
  • Beach Vista construction site, inspection photo 3, 16 December 2020
  • Beach Vista construction site, inspection photo 4, 16 December 2020

26 August 2020

63%+13 pts

  • Beach Vista construction site, inspection photo 1, 26 August 2020
  • Beach Vista construction site, inspection photo 2, 26 August 2020
  • Beach Vista construction site, inspection photo 3, 26 August 2020
  • Beach Vista construction site, inspection photo 4, 26 August 2020

19 May 2020

50%+19 pts

  • Beach Vista construction site, inspection photo 1, 19 May 2020
  • Beach Vista construction site, inspection photo 2, 19 May 2020
  • Beach Vista construction site, inspection photo 3, 19 May 2020
  • Beach Vista construction site, inspection photo 4, 19 May 2020

20 January 2020

31%+10 pts

  • Beach Vista construction site, inspection photo 1, 20 January 2020
  • Beach Vista construction site, inspection photo 2, 20 January 2020
  • Beach Vista construction site, inspection photo 3, 20 January 2020
  • Beach Vista construction site, inspection photo 4, 20 January 2020

10 October 2019

21%+8.7 pts

  • Beach Vista construction site, inspection photo 1, 10 October 2019
  • Beach Vista construction site, inspection photo 2, 10 October 2019
  • Beach Vista construction site, inspection photo 3, 10 October 2019
  • Beach Vista construction site, inspection photo 4, 10 October 2019

3 July 2019

12%+5.1 pts

  • Beach Vista construction site, inspection photo 1, 3 July 2019
  • Beach Vista construction site, inspection photo 2, 3 July 2019
  • Beach Vista construction site, inspection photo 3, 3 July 2019
  • Beach Vista construction site, inspection photo 4, 3 July 2019

All 119 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 36% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Beach Vista?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Beach Vista handover date?
Construction of Beach Vista is recorded as complete, with a registered completion date of January 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Beach Vista?
Beach Vista was 100% built at the site inspection on 26 December 2021. The site has been inspected 13 times since August 2018. The Land Department took 119 site photos at its inspections.
Is Beach Vista delayed?
The register lists construction as complete.
Who is building Beach Vista?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Vista?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.