Beach Mansion construction progress
The register lists Beach Mansion in Dubai Harbour as complete, with a registered completion date of December 2025. Its last site inspection on record was in November 2025. The developer is Emaar Development.
100%
Built, at the site inspection of 10 November 2025
Construction complete
- Registered completion date
- December 2025
- Construction started
- February 2022
- First registered
- September 2021
- Developer
- Emaar Development
- Community
- Dubai Harbour
- Units
- 495
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- بيتش مانشن
- Project number
- 2286
- Site inspections
- 10
Schedule
The register lists Beach Mansion as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
10 November 2025
100%+4.8 pts
17 July 2025
95%+5.2 pts
21 April 2025
90%+9.2 pts
10 December 2024
81%+10 pts
20 August 2024
70%+19 pts
15 February 2024
52%+30 pts
14 September 2023
22%+15 pts
19 April 2023
7.1%+6.8 pts
29 September 2022
0.4%+0.3 pts
6 June 2022
0%
Context
Dubai Harbour has 11 projects under construction, 36% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Beach Mansion?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Beach Mansion handover date?
- Construction of Beach Mansion is recorded as complete, with a registered completion date of December 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Beach Mansion?
- Beach Mansion was 100% built at the site inspection on 10 November 2025. The site has been inspected 10 times since June 2022. The Land Department took 71 site photos at its inspections.
- Is Beach Mansion delayed?
- The register lists construction as complete.
- Who is building Beach Mansion?
- The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
- Which bank holds the escrow account for Beach Mansion?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 45%, Due April 2028.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Sobha Seahaven Tower B & CNearby in Dubai Harbour. 40%, Due October 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
















.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

.jpg&w=3840&q=75)