Beach Isle construction progress

The register lists Beach Isle in Dubai Harbour as complete, with a registered completion date of April 2023. Its last site inspection on record was in May 2023. The developer is Emaar Development.

100%

Built, at the site inspection of 2 May 2023

Construction complete

Registered completion date
April 2023
Construction started
April 2020
First registered
January 2020
Community
Dubai Harbour
Units
397
Escrow bank
Mashreq Bank
Name in Arabic
بيتش آيل
Project number
2207
Site inspections
8

Schedule

The register lists Beach Isle as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 May 2023

100%+14 pts

  • Beach Isle construction site, inspection photo 1, 2 May 2023
  • Beach Isle construction site, inspection photo 2, 2 May 2023
  • Beach Isle construction site, inspection photo 3, 2 May 2023
  • Beach Isle construction site, inspection photo 4, 2 May 2023

28 December 2022

86%+14 pts

  • Beach Isle construction site, inspection photo 1, 28 December 2022
  • Beach Isle construction site, inspection photo 2, 28 December 2022
  • Beach Isle construction site, inspection photo 3, 28 December 2022
  • Beach Isle construction site, inspection photo 4, 28 December 2022

8 September 2022

72%+15 pts

  • Beach Isle construction site, inspection photo 1, 8 September 2022
  • Beach Isle construction site, inspection photo 2, 8 September 2022
  • Beach Isle construction site, inspection photo 3, 8 September 2022
  • Beach Isle construction site, inspection photo 4, 8 September 2022

30 May 2022

57%+24 pts

  • Beach Isle construction site, inspection photo 1, 30 May 2022
  • Beach Isle construction site, inspection photo 2, 30 May 2022
  • Beach Isle construction site, inspection photo 3, 30 May 2022
  • Beach Isle construction site, inspection photo 4, 30 May 2022

27 January 2022

33%+13 pts

  • Beach Isle construction site, inspection photo 1, 27 January 2022
  • Beach Isle construction site, inspection photo 2, 27 January 2022
  • Beach Isle construction site, inspection photo 3, 27 January 2022
  • Beach Isle construction site, inspection photo 4, 27 January 2022

4 October 2021

21%+4.2 pts

  • Beach Isle construction site, inspection photo 1, 4 October 2021
  • Beach Isle construction site, inspection photo 2, 4 October 2021
  • Beach Isle construction site, inspection photo 3, 4 October 2021
  • Beach Isle construction site, inspection photo 4, 4 October 2021

30 June 2021

17%+3.5 pts

  • Beach Isle construction site, inspection photo 1, 30 June 2021
  • Beach Isle construction site, inspection photo 2, 30 June 2021
  • Beach Isle construction site, inspection photo 3, 30 June 2021
  • Beach Isle construction site, inspection photo 4, 30 June 2021

18 March 2021

13%

  • Beach Isle construction site, inspection photo 1, 18 March 2021
  • Beach Isle construction site, inspection photo 2, 18 March 2021
  • Beach Isle construction site, inspection photo 3, 18 March 2021
  • Beach Isle construction site, inspection photo 4, 18 March 2021

All 88 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 36% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Beach Isle?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Beach Isle handover date?
Construction of Beach Isle is recorded as complete, with a registered completion date of April 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Beach Isle?
Beach Isle was 100% built at the site inspection on 2 May 2023. The site has been inspected 8 times since March 2021. The Land Department took 88 site photos at its inspections.
Is Beach Isle delayed?
The register lists construction as complete.
Who is building Beach Isle?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Isle?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.