Dd Stand Point construction progress

The register lists Dd Stand Point in DownTown Dubai as complete, with a registered completion date of December 2012. Its last site inspection on record was in January 2013. The developer is Emaar Properties.

100%

Built, at the site inspection of 27 January 2013

Construction complete

Registered completion date
December 2012
Construction started
April 2012
First registered
July 2010
Units
549
Escrow bank
Mashreq Bank
Name in Arabic
د د ستاند بوينت
Project number
1277
Site inspections
2

Schedule

The register lists Dd Stand Point as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 January 2013

99%+4.5 pts

  • Dd Stand Point construction site, inspection photo 1, 27 January 2013
  • Dd Stand Point construction site, inspection photo 2, 27 January 2013
  • Dd Stand Point construction site, inspection photo 3, 27 January 2013
  • Dd Stand Point construction site, inspection photo 4, 27 January 2013

23 September 2012

95%

  • Dd Stand Point construction site, inspection photo 1, 23 September 2012
  • Dd Stand Point construction site, inspection photo 2, 23 September 2012
  • Dd Stand Point construction site, inspection photo 3, 23 September 2012
  • Dd Stand Point construction site, inspection photo 4, 23 September 2012

All 22 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Dd Stand Point?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Dd Stand Point handover date?
Construction of Dd Stand Point is recorded as complete, with a registered completion date of December 2012. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Dd Stand Point?
Dd Stand Point was 100% built at the site inspection on 27 January 2013. The site has been inspected 2 times since September 2012. The Land Department took 22 site photos at its inspections.
Is Dd Stand Point delayed?
The register lists construction as complete.
Who is building Dd Stand Point?
The registered developer is Emaar Properties. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Dd Stand Point?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.