Baccarat Hotel And Residences, Dubai construction progress
The registered completion date for Baccarat Hotel And Residences, Dubai in DownTown Dubai is December 2026. At the last site inspection, in September 2026, it was 21% built. The developer is Bc Residences.
21%
Built, at the site inspection of 3 September 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- July 2032
- Construction started
- March 2023
- First registered
- September 2023
- Developer
- Bc Residences
- Community
- DownTown Dubai
- Units
- 98
- Escrow bank
- Emirates NBD
- Name in Arabic
- فندق ومساكن بكارات ، دبي
- Project number
- 2724
- Site inspections
- 7
Schedule
Between October 2025 and September 2026 the site added about 1.1 points a month. At that rate it would finish around July 2032, more than three months after its registered date of December 2026.
Site inspections
3 September 2026
21%+3.1 pts
2 June 2026
18%+5.1 pts
29 January 2026
13%+3.6 pts
14 October 2025
9.3%+2.0 pts
4 June 2025
7.3%+0.7 pts
6 December 2024
6.5%+6.5 pts
28 July 2023
0%
Context
DownTown Dubai has 13 projects under construction, 35% built on average.
Own a unit in Baccarat Hotel And Residences, Dubai?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Baccarat Hotel And Residences, Dubai handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Baccarat Hotel And Residences, Dubai?
- Baccarat Hotel And Residences, Dubai was 21% built at the site inspection on 3 September 2026. The site has been inspected 7 times since July 2023. The Land Department took 42 site photos at its inspections.
- Is Baccarat Hotel And Residences, Dubai delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Baccarat Hotel And Residences, Dubai?
- The registered developer is Bc Residences.
- Which bank holds the escrow account for Baccarat Hotel And Residences, Dubai?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiNearby in DownTown Dubai. 76%, Due December 2026.
- City Center ResidencesNearby in DownTown Dubai. 72%, Due September 2026, passed.
- Mercedes-Benz Places | BinghattiNearby in DownTown Dubai. 65%, Due December 2026.
- Rove Home Residences By IrthNearby in DownTown Dubai. 63%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.