Verdana Residence 2 construction progress

Verdana Residence 2 in Dubai Investment Park First was registered to complete in April 2026 and is still under construction. At the last site inspection, in June 2026, it was 20% built. The developer is Reportage Prime Properties.

20%

Built, at the site inspection of 3 June 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
April 2032
Construction started
October 2024
First registered
August 2024
Units
239
Escrow bank
Al Masraf
Name in Arabic
فيردانا ريزيدانس 2
Project number
2976
Site inspections
5

Schedule

Verdana Residence 2 was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around April 2032.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 June 2026

20%+5.1 pts

  • Verdana Residence 2 construction site, inspection photo 1, 3 June 2026
  • Verdana Residence 2 construction site, inspection photo 2, 3 June 2026
  • Verdana Residence 2 construction site, inspection photo 3, 3 June 2026
  • Verdana Residence 2 construction site, inspection photo 4, 3 June 2026

11 February 2026

15%+7.8 pts

  • Verdana Residence 2 construction site, inspection photo 1, 11 February 2026
  • Verdana Residence 2 construction site, inspection photo 2, 11 February 2026
  • Verdana Residence 2 construction site, inspection photo 3, 11 February 2026
  • Verdana Residence 2 construction site, inspection photo 4, 11 February 2026

21 June 2025

7.1%+7.1 pts

  • Verdana Residence 2 construction site, inspection photo 1, 21 June 2025
  • Verdana Residence 2 construction site, inspection photo 2, 21 June 2025
  • Verdana Residence 2 construction site, inspection photo 3, 21 June 2025
  • Verdana Residence 2 construction site, inspection photo 4, 21 June 2025

23 December 2024

0%

  • Verdana Residence 2 construction site, inspection photo 1, 23 December 2024
  • Verdana Residence 2 construction site, inspection photo 2, 23 December 2024

29 March 2024

0%

  • Verdana Residence 2 construction site, inspection photo 1, 29 March 2024
  • Verdana Residence 2 construction site, inspection photo 2, 29 March 2024
  • Verdana Residence 2 construction site, inspection photo 3, 29 March 2024

All 21 site photos, by inspection date

Context

Dubai Investment Park First has 9 projects under construction, 44% built on average.

Reportage Prime Properties has 9 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Verdana Residence 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verdana Residence 2 handover date?
The registered completion date was April 2026, and the register still lists Verdana Residence 2 as under construction. At the pace of its recent inspections the site would reach 100% around April 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Verdana Residence 2?
Verdana Residence 2 was 20% built at the site inspection on 3 June 2026. The site has been inspected 5 times since March 2024. The Land Department took 21 site photos at its inspections.
Is Verdana Residence 2 delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Verdana Residence 2?
The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Verdana Residence 2?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.