Reportage Hills construction progress

The registered completion date for Reportage Hills in Al Hebiah Fifth is June 2028. At the last site inspection, in June 2026, it was 0.4% built. The developer is Reportage Prime Properties.

0.4%

Built, at the site inspection of 4 June 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
July 2178
Construction started
June 2025
First registered
January 2025
Units
905
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ريبورتاج هيلز
Project number
3465
Site inspections
4

Schedule

Between November 2025 and June 2026 the site added about 0.1 points a month. At that rate it would finish around July 2178, more than three months after its registered date of June 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 June 2026

0.4%+0.2 pts

  • Reportage Hills construction site, inspection photo 1, 4 June 2026
  • Reportage Hills construction site, inspection photo 2, 4 June 2026
  • Reportage Hills construction site, inspection photo 3, 4 June 2026
  • Reportage Hills construction site, inspection photo 4, 4 June 2026

3 February 2026

0.2%+0.2 pts

  • Reportage Hills construction site, inspection photo 1, 3 February 2026
  • Reportage Hills construction site, inspection photo 2, 3 February 2026
  • Reportage Hills construction site, inspection photo 3, 3 February 2026
  • Reportage Hills construction site, inspection photo 4, 3 February 2026

4 November 2025

0%+0.0 pts

  • Reportage Hills construction site, inspection photo 1, 4 November 2025
  • Reportage Hills construction site, inspection photo 2, 4 November 2025
  • Reportage Hills construction site, inspection photo 3, 4 November 2025
  • Reportage Hills construction site, inspection photo 4, 4 November 2025

23 December 2024

0%

  • Reportage Hills construction site, inspection photo 1, 23 December 2024
  • Reportage Hills construction site, inspection photo 2, 23 December 2024

All 15 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 49% built on average.

Reportage Prime Properties has 9 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Reportage Hills?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Reportage Hills handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2178. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Reportage Hills?
Reportage Hills was 0.4% built at the site inspection on 4 June 2026. The site has been inspected 4 times since December 2024. The Land Department took 15 site photos at its inspections.
Is Reportage Hills delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Reportage Hills?
The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Reportage Hills?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.