Reportage Hills construction progress
The registered completion date for Reportage Hills in Al Hebiah Fifth is June 2028. At the last site inspection, in June 2026, it was 0.4% built. The developer is Reportage Prime Properties.
0.4%
Built, at the site inspection of 4 June 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- July 2178
- Construction started
- June 2025
- First registered
- January 2025
- Developer
- Reportage Prime Properties
- Community
- Al Hebiah Fifth
- Units
- 905
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- ريبورتاج هيلز
- Project number
- 3465
- Site inspections
- 4
Schedule
Between November 2025 and June 2026 the site added about 0.1 points a month. At that rate it would finish around July 2178, more than three months after its registered date of June 2028.
Site inspections
4 June 2026
0.4%+0.2 pts
3 February 2026
0.2%+0.2 pts
4 November 2025
0%+0.0 pts
23 December 2024
0%
Context
Al Hebiah Fifth has 20 projects under construction, 49% built on average.
Reportage Prime Properties has 9 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Reportage Hills?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Reportage Hills handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2178. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Reportage Hills?
- Reportage Hills was 0.4% built at the site inspection on 4 June 2026. The site has been inspected 4 times since December 2024. The Land Department took 15 site photos at its inspections.
- Is Reportage Hills delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Reportage Hills?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Reportage Hills?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana (Phase 1)Also by Reportage Prime Properties. 95%, Due December 2025, passed.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%, Due December 2025, passed.
- Verdana ResidenceAlso by Reportage Prime Properties. 96%, Due December 2025, passed.
- BiancaAlso by Reportage Prime Properties. 56%, Due December 2026.
- Paradise HillsNearby in Al Hebiah Fifth. 84%, Due December 2025, passed.
- Damac Lagoons - IbizaNearby in Al Hebiah Fifth. 79%, Due December 2025, passed.
- Damac Lagoons - MykonosNearby in Al Hebiah Fifth. 81%, Due December 2025, passed.
- Damac Lagoons - Monte CarloNearby in Al Hebiah Fifth. 86%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)