Verdana 2 construction progress

No completion date is registered for Verdana 2 in Dubai Investment Park First yet. At the last site inspection, in June 2026, it was 56% built. The developer is Reportage Prime Properties.

56%

Built, at the site inspection of 3 June 2026

Finish at recent pace
January 2028
Construction started
December 2023
First registered
November 2023
Units
209
Escrow bank
Al Masraf
Name in Arabic
فيردانا 2
Project number
2720
Site inspections
8

Schedule

Since October 2025 Verdana 2 has added about 2.3 points a month. At that rate the site reaches 100% around January 2028. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

3 June 2026

56%+6.0 pts

  • Verdana 2 construction site, inspection photo 1, 3 June 2026
  • Verdana 2 construction site, inspection photo 2, 3 June 2026
  • Verdana 2 construction site, inspection photo 3, 3 June 2026
  • Verdana 2 construction site, inspection photo 4, 3 June 2026

11 February 2026

50%+11 pts

  • Verdana 2 construction site, inspection photo 1, 11 February 2026
  • Verdana 2 construction site, inspection photo 2, 11 February 2026
  • Verdana 2 construction site, inspection photo 3, 11 February 2026
  • Verdana 2 construction site, inspection photo 4, 11 February 2026

20 October 2025

39%+16 pts

  • Verdana 2 construction site, inspection photo 1, 20 October 2025
  • Verdana 2 construction site, inspection photo 2, 20 October 2025
  • Verdana 2 construction site, inspection photo 3, 20 October 2025
  • Verdana 2 construction site, inspection photo 4, 20 October 2025

17 March 2025

23%+12 pts

  • Verdana 2 construction site, inspection photo 1, 17 March 2025
  • Verdana 2 construction site, inspection photo 2, 17 March 2025
  • Verdana 2 construction site, inspection photo 3, 17 March 2025
  • Verdana 2 construction site, inspection photo 4, 17 March 2025

6 November 2024

11%+9.8 pts

  • Verdana 2 construction site, inspection photo 1, 6 November 2024
  • Verdana 2 construction site, inspection photo 2, 6 November 2024
  • Verdana 2 construction site, inspection photo 3, 6 November 2024
  • Verdana 2 construction site, inspection photo 4, 6 November 2024

26 March 2024

1.1%+0.7 pts

  • Verdana 2 construction site, inspection photo 1, 26 March 2024
  • Verdana 2 construction site, inspection photo 2, 26 March 2024

6 December 2023

0.3%+0.3 pts

  • Verdana 2 construction site, inspection photo 1, 6 December 2023
  • Verdana 2 construction site, inspection photo 2, 6 December 2023
  • Verdana 2 construction site, inspection photo 3, 6 December 2023
  • Verdana 2 construction site, inspection photo 4, 6 December 2023

25 September 2023

0%

  • Verdana 2 construction site, inspection photo 1, 25 September 2023
  • Verdana 2 construction site, inspection photo 2, 25 September 2023
  • Verdana 2 construction site, inspection photo 3, 25 September 2023
  • Verdana 2 construction site, inspection photo 4, 25 September 2023

All 48 site photos, by inspection date

Context

Dubai Investment Park First has 9 projects under construction, 44% built on average.

Reportage Prime Properties has 9 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Verdana 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verdana 2 handover date?
No completion date is on record for Verdana 2 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Verdana 2?
Verdana 2 was 56% built at the site inspection on 3 June 2026. The site has been inspected 8 times since September 2023. The Land Department took 48 site photos at its inspections.
Who is building Verdana 2?
The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Verdana 2?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.