Verdana 2 construction progress
Verdana 2 in Dubai Investment Park First is 56% built at the Land Department inspection of June 2026. Developer Reportage Prime Properties.
56%
Built, at the Land Department site inspection of 3 June 2026
- Finish at recent pace
- January 2028
- Construction started
- December 2023
- Registered with the Land Department
- November 2023
- Developer
- Reportage Prime Properties
- Community
- Dubai Investment Park First
- Units
- 209
- Escrow bank
- Al Masraf
- Name in Arabic
- فيردانا 2
- Land Department project number
- 2720
- Land Department site inspections
- 8
Schedule
Since October 2025 Verdana 2 has added about 2.3 points a month. At that rate the site reaches 100% around January 2028. The Land Department has no completion date on record to compare it with.
Site inspections
3 June 2026
56%+6.0 pts
11 February 2026
50%+11 pts
20 October 2025
39%+16 pts
17 March 2025
23%+12 pts
6 November 2024
11%+9.8 pts
26 March 2024
1.1%+0.7 pts
6 December 2023
0.3%+0.3 pts
25 September 2023
0%
Context
Dubai Investment Park First has 9 projects under construction, 44% built on average.
Reportage Prime Properties has 9 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Verdana 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Verdana 2 be completed?
- The Land Department has no completion date on record for Verdana 2 yet.
- How much of Verdana 2 is built?
- 56%, measured at the Land Department site inspection on 3 June 2026. The Land Department engineers have inspected the site 8 times since September 2023.
- Who is building Verdana 2?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Verdana 2?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana (Phase 1)Also by Reportage Prime Properties. 95%, Due December 2025, passed.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%.
- Verdana ResidenceAlso by Reportage Prime Properties. 96%, Due December 2025, passed.
- BiancaAlso by Reportage Prime Properties. 56%, Due December 2026.
- Olivia ResidencesNearby in Dubai Investment Park First. 38%, Due December 2026.
- Verdana 3Nearby in Dubai Investment Park First. 0.1%, Due September 2028.
- Verdana Residence 3Nearby in Dubai Investment Park First. 0%, Due September 2028.
- Verdana Residence 4Nearby in Dubai Investment Park First. 0%, Due September 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)