Taormina Village 1 construction progress

The registered completion date for Taormina Village 1 in Wadi Al Safa 3 is December 2027. At the last site inspection, in June 2026, it was 20% built. The developer is Reportage Prime Properties.

20%

Built, at the site inspection of 3 June 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
March 2030
Construction started
December 2024
First registered
September 2024
Units
530
Escrow bank
Commercial Bank of Dubai
Name in Arabic
تاورمينا فيلدج 1
Project number
3108
Site inspections
5

Schedule

Between October 2025 and June 2026 the site added about 1.8 points a month. At that rate it would finish around March 2030, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 June 2026

20%+4.4 pts

  • Taormina Village 1 construction site, inspection photo 1, 3 June 2026
  • Taormina Village 1 construction site, inspection photo 2, 3 June 2026
  • Taormina Village 1 construction site, inspection photo 3, 3 June 2026
  • Taormina Village 1 construction site, inspection photo 4, 3 June 2026

6 February 2026

16%+8.7 pts

  • Taormina Village 1 construction site, inspection photo 1, 6 February 2026
  • Taormina Village 1 construction site, inspection photo 2, 6 February 2026
  • Taormina Village 1 construction site, inspection photo 3, 6 February 2026
  • Taormina Village 1 construction site, inspection photo 4, 6 February 2026

20 October 2025

7.3%+7.3 pts

  • Taormina Village 1 construction site, inspection photo 1, 20 October 2025
  • Taormina Village 1 construction site, inspection photo 2, 20 October 2025
  • Taormina Village 1 construction site, inspection photo 3, 20 October 2025
  • Taormina Village 1 construction site, inspection photo 4, 20 October 2025

17 March 2025

0%+0.0 pts

  • Taormina Village 1 construction site, inspection photo 1, 17 March 2025
  • Taormina Village 1 construction site, inspection photo 2, 17 March 2025
  • Taormina Village 1 construction site, inspection photo 3, 17 March 2025

30 May 2024

0%

  • Taormina Village 1 construction site, inspection photo 1, 30 May 2024
  • Taormina Village 1 construction site, inspection photo 2, 30 May 2024
  • Taormina Village 1 construction site, inspection photo 3, 30 May 2024

All 36 site photos, by inspection date

Context

Wadi Al Safa 3 has 3 projects under construction, 7.8% built on average.

Reportage Prime Properties has 9 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Taormina Village 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Taormina Village 1 handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Taormina Village 1?
Taormina Village 1 was 20% built at the site inspection on 3 June 2026. The site has been inspected 5 times since May 2024. The Land Department took 36 site photos at its inspections.
Is Taormina Village 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Taormina Village 1?
The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Taormina Village 1?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.