Taormina Village 1 construction progress
The registered completion date for Taormina Village 1 in Wadi Al Safa 3 is December 2027. At the last site inspection, in June 2026, it was 20% built. The developer is Reportage Prime Properties.
20%
Built, at the site inspection of 3 June 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- March 2030
- Construction started
- December 2024
- First registered
- September 2024
- Developer
- Reportage Prime Properties
- Community
- Wadi Al Safa 3
- Units
- 530
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- تاورمينا فيلدج 1
- Project number
- 3108
- Site inspections
- 5
Schedule
Between October 2025 and June 2026 the site added about 1.8 points a month. At that rate it would finish around March 2030, more than three months after its registered date of December 2027.
Site inspections
3 June 2026
20%+4.4 pts
6 February 2026
16%+8.7 pts
20 October 2025
7.3%+7.3 pts
17 March 2025
0%+0.0 pts
30 May 2024
0%
Context
Wadi Al Safa 3 has 3 projects under construction, 7.8% built on average.
Reportage Prime Properties has 9 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Taormina Village 1?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Taormina Village 1 handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Taormina Village 1?
- Taormina Village 1 was 20% built at the site inspection on 3 June 2026. The site has been inspected 5 times since May 2024. The Land Department took 36 site photos at its inspections.
- Is Taormina Village 1 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Taormina Village 1?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Taormina Village 1?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana (Phase 1)Also by Reportage Prime Properties. 95%, Due December 2025, passed.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%, Due December 2025, passed.
- Verdana ResidenceAlso by Reportage Prime Properties. 96%, Due December 2025, passed.
- BiancaAlso by Reportage Prime Properties. 56%, Due December 2026.
- The Wilds 3Nearby in Wadi Al Safa 3. 3.1%, Due May 2029.
- Taormina Village 2Nearby in Wadi Al Safa 3. 0%, Due July 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)