Beachfront Gates 1 construction progress

The registered completion date for Beachfront Gates 1 in Dubai South Residential District is December 2026. At the last site inspection, in April 2026, it was 36% built. The developer is Dubai South Properties Dwc.

36%

Built, at the site inspection of 14 April 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
September 2028
Construction started
February 2025
First registered
February 2025
Units
74
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بوابات الشاطئ 1
Project number
3377
Site inspections
2

Schedule

Between November 2024 and April 2026 the site added about 2.2 points a month. At that rate it would finish around September 2028, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 April 2026

36%+36 pts

  • Beachfront Gates 1 construction site, inspection photo 1, 14 April 2026
  • Beachfront Gates 1 construction site, inspection photo 2, 14 April 2026
  • Beachfront Gates 1 construction site, inspection photo 3, 14 April 2026
  • Beachfront Gates 1 construction site, inspection photo 4, 14 April 2026

19 November 2024

0%

  • Beachfront Gates 1 construction site, inspection photo 1, 19 November 2024
  • Beachfront Gates 1 construction site, inspection photo 2, 19 November 2024

All 12 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Beachfront Gates 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Beachfront Gates 1 handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Beachfront Gates 1?
Beachfront Gates 1 was 36% built at the site inspection on 14 April 2026. The site has been inspected 2 times since November 2024. The Land Department took 12 site photos at its inspections.
Is Beachfront Gates 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Beachfront Gates 1?
The registered developer is Dubai South Properties Dwc. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Beachfront Gates 1?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.