Beachfront Gates 2 construction progress

Beachfront Gates 2 in Dubai South Residential District is 42% built at the Land Department inspection of July 2026. Developer Dubai South Properties Dwc. Completion registered for December 2026.

42%

Built, at the Land Department site inspection of 14 July 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
September 2027
Construction started
February 2025
Registered with the Land Department
February 2025
Units
162
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بوابات الشاطئ 2
Land Department project number
3379
Land Department site inspections
3

Schedule

Between February 2026 and July 2026 the site added about 4.2 points a month. At that rate it would finish around September 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 July 2026

42%+21 pts

  • Beachfront Gates 2 construction site, Land Department inspection photo 1, 14 July 2026
  • Beachfront Gates 2 construction site, Land Department inspection photo 2, 14 July 2026
  • Beachfront Gates 2 construction site, Land Department inspection photo 3, 14 July 2026
  • Beachfront Gates 2 construction site, Land Department inspection photo 4, 14 July 2026

11 February 2026

21%+21 pts

  • Beachfront Gates 2 construction site, Land Department inspection photo 1, 11 February 2026
  • Beachfront Gates 2 construction site, Land Department inspection photo 2, 11 February 2026
  • Beachfront Gates 2 construction site, Land Department inspection photo 3, 11 February 2026
  • Beachfront Gates 2 construction site, Land Department inspection photo 4, 11 February 2026

19 November 2024

0%

  • Beachfront Gates 2 construction site, Land Department inspection photo 1, 19 November 2024
  • Beachfront Gates 2 construction site, Land Department inspection photo 2, 19 November 2024

All 16 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average.

Dubai South Properties Dwc has 17 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Beachfront Gates 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Beachfront Gates 2 be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around September 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Beachfront Gates 2 is built?
42%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 3 times since November 2024.
Is Beachfront Gates 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Beachfront Gates 2?
The registered developer is Dubai South Properties Dwc. It has 16 other projects under construction in Dubai.
Which bank holds the escrow account for Beachfront Gates 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.