South Bay 5 Premium in Dubai South Residential District is 78% built at the Land Department inspection of July 2026. Developer Dubai South Properties Dwc.

78%

Built, at the Land Department site inspection of 23 July 2026

Finish at recent pace
December 2026
Construction started
June 2024
Registered with the Land Department
April 2024
Units
144
Escrow bank
Dubai Islamic Bank
Name in Arabic
خليج الجنوب 5 بريميوم
Land Department project number
2985
Land Department site inspections
4

Schedule

Since July 2025 South Bay 5 Premium has added about 4.3 points a month. At that rate the site reaches 100% around December 2026. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

23 July 2026

78%+34 pts

  • South Bay 5 Premium construction site, Land Department inspection photo 1, 23 July 2026
  • South Bay 5 Premium construction site, Land Department inspection photo 2, 23 July 2026
  • South Bay 5 Premium construction site, Land Department inspection photo 3, 23 July 2026
  • South Bay 5 Premium construction site, Land Department inspection photo 4, 23 July 2026

11 February 2026

44%+17 pts

  • South Bay 5 Premium construction site, Land Department inspection photo 1, 11 February 2026
  • South Bay 5 Premium construction site, Land Department inspection photo 2, 11 February 2026
  • South Bay 5 Premium construction site, Land Department inspection photo 3, 11 February 2026
  • South Bay 5 Premium construction site, Land Department inspection photo 4, 11 February 2026

29 July 2025

27%+27 pts

  • South Bay 5 Premium construction site, Land Department inspection photo 1, 29 July 2025
  • South Bay 5 Premium construction site, Land Department inspection photo 2, 29 July 2025
  • South Bay 5 Premium construction site, Land Department inspection photo 3, 29 July 2025
  • South Bay 5 Premium construction site, Land Department inspection photo 4, 29 July 2025

27 March 2024

0%

  • South Bay 5 Premium construction site, Land Department inspection photo 1, 27 March 2024
  • South Bay 5 Premium construction site, Land Department inspection photo 2, 27 March 2024

All 26 site photos, by inspection date

Context

Dubai South Residential District has 40 projects under construction, 40% built on average.

Dubai South Properties Dwc has 17 projects under construction in Dubai, none past their registered completion dates.

Own a unit in South Bay 5 Premium?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will South Bay 5 Premium be completed?
The Land Department has no completion date on record for South Bay 5 Premium yet.
How much of South Bay 5 Premium is built?
78%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 4 times since March 2024.
Who is building South Bay 5 Premium?
The registered developer is Dubai South Properties Dwc. It has 16 other projects under construction in Dubai.
Which bank holds the escrow account for South Bay 5 Premium?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.