Royal Regency construction progress

The register lists Royal Regency in Business Bay as complete, with a registered completion date of February 2026. Its last site inspection on record was in October 2025. The developer is Alseeb Real Estate Development.

100%

Built, at the site inspection of 24 October 2025

Construction complete

Registered completion date
February 2026
Construction started
November 2022
First registered
September 2023
Community
Business Bay
Units
165
Escrow bank
Sharjah Islamic Bank
Name in Arabic
رويال ريجينسي
Project number
2654
Site inspections
9

Schedule

The register lists Royal Regency as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 October 2025

100%+2.7 pts

  • Royal Regency construction site, inspection photo 1, 24 October 2025
  • Royal Regency construction site, inspection photo 2, 24 October 2025
  • Royal Regency construction site, inspection photo 3, 24 October 2025
  • Royal Regency construction site, inspection photo 4, 24 October 2025

14 July 2025

97%+1.5 pts

  • Royal Regency construction site, inspection photo 1, 14 July 2025
  • Royal Regency construction site, inspection photo 2, 14 July 2025
  • Royal Regency construction site, inspection photo 3, 14 July 2025
  • Royal Regency construction site, inspection photo 4, 14 July 2025

18 March 2025

96%+16 pts

  • Royal Regency construction site, inspection photo 1, 18 March 2025
  • Royal Regency construction site, inspection photo 2, 18 March 2025
  • Royal Regency construction site, inspection photo 3, 18 March 2025
  • Royal Regency construction site, inspection photo 4, 18 March 2025

28 October 2024

79%+16 pts

  • Royal Regency construction site, inspection photo 1, 28 October 2024
  • Royal Regency construction site, inspection photo 2, 28 October 2024
  • Royal Regency construction site, inspection photo 3, 28 October 2024
  • Royal Regency construction site, inspection photo 4, 28 October 2024

25 July 2024

64%+8.8 pts

  • Royal Regency construction site, inspection photo 1, 25 July 2024
  • Royal Regency construction site, inspection photo 2, 25 July 2024
  • Royal Regency construction site, inspection photo 3, 25 July 2024
  • Royal Regency construction site, inspection photo 4, 25 July 2024

26 April 2024

55%+30 pts

  • Royal Regency construction site, inspection photo 1, 26 April 2024
  • Royal Regency construction site, inspection photo 2, 26 April 2024
  • Royal Regency construction site, inspection photo 3, 26 April 2024
  • Royal Regency construction site, inspection photo 4, 26 April 2024

26 September 2023

25%+7.4 pts

  • Royal Regency construction site, inspection photo 1, 26 September 2023
  • Royal Regency construction site, inspection photo 2, 26 September 2023
  • Royal Regency construction site, inspection photo 3, 26 September 2023
  • Royal Regency construction site, inspection photo 4, 26 September 2023

20 June 2023

17%+2.5 pts

  • Royal Regency construction site, inspection photo 1, 20 June 2023
  • Royal Regency construction site, inspection photo 2, 20 June 2023
  • Royal Regency construction site, inspection photo 3, 20 June 2023
  • Royal Regency construction site, inspection photo 4, 20 June 2023

10 May 2023

15%

  • Royal Regency construction site, inspection photo 1, 10 May 2023
  • Royal Regency construction site, inspection photo 2, 10 May 2023
  • Royal Regency construction site, inspection photo 3, 10 May 2023
  • Royal Regency construction site, inspection photo 4, 10 May 2023

All 77 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Alseeb Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Royal Regency?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Royal Regency handover date?
Construction of Royal Regency is recorded as complete, with a registered completion date of February 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Royal Regency?
Royal Regency was 100% built at the site inspection on 24 October 2025. The site has been inspected 9 times since May 2023. The Land Department took 77 site photos at its inspections.
Is Royal Regency delayed?
The register lists construction as complete.
Who is building Royal Regency?
The registered developer is Alseeb Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Royal Regency?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.