Royal Regency construction photos

77 photos from 9 site inspections, newest first. The percentage is how much of Royal Regency was built on the day of each visit.

24 October 2025100% built

14 July 202597% built

18 March 202596% built

28 October 202479% built

25 July 202464% built

26 April 202455% built

26 September 202325% built

20 June 202317% built

10 May 202315% built

Back to Royal Regency construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.