The Chedi Private Residences construction progress
The registered completion date for The Chedi Private Residences in Barsha Heights is February 2029. At the last site inspection, in September 2026, it was 2.6% built. The developer is Alseeb Real Estate Development.
2.6%
Built, at the site inspection of 8 September 2026
Running behind its date
- Registered completion date
- February 2029
- Finish at recent pace
- June 2062
- Construction started
- March 2025
- First registered
- December 2024
- Developer
- Alseeb Real Estate Development
- Community
- Barsha Heights
- Units
- 118
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مساكن ذا شيدي الخاصة
- Project number
- 3323
- Site inspections
- 4
Schedule
Between September 2025 and September 2026 the site added about 0.2 points a month. At that rate it would finish around June 2062, more than three months after its registered date of February 2029.
Site inspections
8 September 2026
2.6%+1.2 pts
12 May 2026
1.4%+1.4 pts
24 September 2025
0%+0.0 pts
7 October 2024
0%
Context
Barsha Heights has 2 projects under construction, 4.8% built on average.
Alseeb Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Chedi Private Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Chedi Private Residences handover date?
- The registered completion date is February 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2062. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Chedi Private Residences?
- The Chedi Private Residences was 2.6% built at the site inspection on 8 September 2026. The site has been inspected 4 times since October 2024. The Land Department took 17 site photos at its inspections.
- Is The Chedi Private Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2029.
- Who is building The Chedi Private Residences?
- The registered developer is Alseeb Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Chedi Private Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Royal Regency SuitesAlso by Alseeb Real Estate Development. 57%, Due December 2026.
- The One By Prestige OneNearby in Barsha Heights. 7.0%, Due June 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)