The Chedi Private Residences construction progress
The Chedi Private Residences in Barsha Heights is 2.6% built at the Land Department inspection of September 2026. Developer Alseeb Real Estate Development. Completion registered for February 2029.
2.6%
Built, at the Land Department site inspection of 8 September 2026
Running behind its date
- Completion date (Land Department)
- February 2029
- Finish at recent pace
- June 2062
- Construction started
- March 2025
- Registered with the Land Department
- December 2024
- Developer
- Alseeb Real Estate Development
- Community
- Barsha Heights
- Units
- 118
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مساكن ذا شيدي الخاصة
- Land Department project number
- 3323
- Land Department site inspections
- 4
Schedule
Between September 2025 and September 2026 the site added about 0.2 points a month. At that rate it would finish around June 2062, more than three months after the February 2029 date registered with the Land Department.
Site inspections
8 September 2026
2.6%+1.2 pts
12 May 2026
1.4%+1.4 pts
24 September 2025
0%+0.0 pts
7 October 2024
0%
Context
Barsha Heights has 2 projects under construction, 4.8% built on average. The Chedi Private Residences is behind that average.
Alseeb Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Chedi Private Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will The Chedi Private Residences be completed?
- The completion date registered with the Dubai Land Department is February 2029. At the pace of its recent inspections the site would reach 100% around June 2062. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Chedi Private Residences is built?
- 2.6%, measured at the Land Department site inspection on 8 September 2026. The Land Department engineers have inspected the site 4 times since October 2024.
- Is The Chedi Private Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2029.
- Who is building The Chedi Private Residences?
- The registered developer is Alseeb Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Chedi Private Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)