Skip to content

Peninsula Two construction progress

The register lists Peninsula Two in Business Bay as complete, with a registered completion date of September 2024. Its last site inspection on record was in February 2026. The developer is Select Global Development.

100%

Built, at the site inspection of 12 February 2026

Construction complete

Registered completion date
September 2024
Construction started
November 2021
First registered
November 2021
Community
Business Bay
Units
462
Escrow bank
Emirates NBD
Name in Arabic
بينينسولا تو
Project number
2318
Site inspections
9

Schedule

The register lists Peninsula Two as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20222023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 February 2026

100%+1.3 pts

  • Peninsula Two construction site, inspection photo 1, 12 February 2026
  • Peninsula Two construction site, inspection photo 2, 12 February 2026
  • Peninsula Two construction site, inspection photo 3, 12 February 2026
  • Peninsula Two construction site, inspection photo 4, 12 February 2026

28 January 2026

99%+3.2 pts

  • Peninsula Two construction site, inspection photo 1, 28 January 2026
  • Peninsula Two construction site, inspection photo 2, 28 January 2026
  • Peninsula Two construction site, inspection photo 3, 28 January 2026
  • Peninsula Two construction site, inspection photo 4, 28 January 2026

27 August 2025

96%+14 pts

  • Peninsula Two construction site, inspection photo 1, 27 August 2025
  • Peninsula Two construction site, inspection photo 2, 27 August 2025
  • Peninsula Two construction site, inspection photo 3, 27 August 2025
  • Peninsula Two construction site, inspection photo 4, 27 August 2025

21 February 2025

81%+19 pts

  • Peninsula Two construction site, inspection photo 1, 21 February 2025
  • Peninsula Two construction site, inspection photo 2, 21 February 2025
  • Peninsula Two construction site, inspection photo 3, 21 February 2025
  • Peninsula Two construction site, inspection photo 4, 21 February 2025

18 October 2024

62%+12 pts

  • Peninsula Two construction site, inspection photo 1, 18 October 2024
  • Peninsula Two construction site, inspection photo 2, 18 October 2024
  • Peninsula Two construction site, inspection photo 3, 18 October 2024
  • Peninsula Two construction site, inspection photo 4, 18 October 2024

9 July 2024

50%+11 pts

  • Peninsula Two construction site, inspection photo 1, 9 July 2024
  • Peninsula Two construction site, inspection photo 2, 9 July 2024
  • Peninsula Two construction site, inspection photo 3, 9 July 2024
  • Peninsula Two construction site, inspection photo 4, 9 July 2024

14 February 2024

39%+20 pts

  • Peninsula Two construction site, inspection photo 1, 14 February 2024
  • Peninsula Two construction site, inspection photo 2, 14 February 2024
  • Peninsula Two construction site, inspection photo 3, 14 February 2024
  • Peninsula Two construction site, inspection photo 4, 14 February 2024

16 August 2023

18%+14 pts

  • Peninsula Two construction site, inspection photo 1, 16 August 2023
  • Peninsula Two construction site, inspection photo 2, 16 August 2023
  • Peninsula Two construction site, inspection photo 3, 16 August 2023
  • Peninsula Two construction site, inspection photo 4, 16 August 2023

20 July 2022

4.6%

  • Peninsula Two construction site, inspection photo 1, 20 July 2022
  • Peninsula Two construction site, inspection photo 2, 20 July 2022
  • Peninsula Two construction site, inspection photo 3, 20 July 2022
  • Peninsula Two construction site, inspection photo 4, 20 July 2022

All 82 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Peninsula Two?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Peninsula Two handover date?
Construction of Peninsula Two is recorded as complete, with a registered completion date of September 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Peninsula Two?
Peninsula Two was 100% built at the site inspection on 12 February 2026. The site has been inspected 9 times since July 2022. The Land Department took 82 site photos at its inspections.
Is Peninsula Two delayed?
The register lists construction as complete.
Who is building Peninsula Two?
The registered developer is Select Global Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Peninsula Two?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.