Peninsula Three construction progress

The register lists Peninsula Three in Business Bay as complete, with a registered completion date of June 2025. Its last site inspection on record was in November 2025. The developer is Select Global Development.

100%

Built, at the site inspection of 27 November 2025

Construction complete

Registered completion date
June 2025
Construction started
June 2022
First registered
March 2022
Community
Business Bay
Units
859
Escrow bank
Dubai Islamic Bank
Name in Arabic
بينينسولا ثري
Project number
2372
Site inspections
8

Schedule

The register lists Peninsula Three as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 November 2025

100%+6.9 pts

  • Peninsula Three construction site, inspection photo 1, 27 November 2025
  • Peninsula Three construction site, inspection photo 2, 27 November 2025
  • Peninsula Three construction site, inspection photo 3, 27 November 2025
  • Peninsula Three construction site, inspection photo 4, 27 November 2025

21 August 2025

93%+15 pts

  • Peninsula Three construction site, inspection photo 1, 21 August 2025
  • Peninsula Three construction site, inspection photo 2, 21 August 2025
  • Peninsula Three construction site, inspection photo 3, 21 August 2025
  • Peninsula Three construction site, inspection photo 4, 21 August 2025

27 March 2025

78%+26 pts

  • Peninsula Three construction site, inspection photo 1, 27 March 2025
  • Peninsula Three construction site, inspection photo 2, 27 March 2025
  • Peninsula Three construction site, inspection photo 3, 27 March 2025
  • Peninsula Three construction site, inspection photo 4, 27 March 2025

31 October 2024

52%+22 pts

  • Peninsula Three construction site, inspection photo 1, 31 October 2024
  • Peninsula Three construction site, inspection photo 2, 31 October 2024
  • Peninsula Three construction site, inspection photo 3, 31 October 2024
  • Peninsula Three construction site, inspection photo 4, 31 October 2024

24 June 2024

30%+15 pts

  • Peninsula Three construction site, inspection photo 1, 24 June 2024
  • Peninsula Three construction site, inspection photo 2, 24 June 2024
  • Peninsula Three construction site, inspection photo 3, 24 June 2024
  • Peninsula Three construction site, inspection photo 4, 24 June 2024

3 January 2024

15%+8.1 pts

  • Peninsula Three construction site, inspection photo 1, 3 January 2024
  • Peninsula Three construction site, inspection photo 2, 3 January 2024
  • Peninsula Three construction site, inspection photo 3, 3 January 2024
  • Peninsula Three construction site, inspection photo 4, 3 January 2024

14 August 2023

6.9%+3.6 pts

  • Peninsula Three construction site, inspection photo 1, 14 August 2023
  • Peninsula Three construction site, inspection photo 2, 14 August 2023
  • Peninsula Three construction site, inspection photo 3, 14 August 2023
  • Peninsula Three construction site, inspection photo 4, 14 August 2023

22 February 2023

3.3%

  • Peninsula Three construction site, inspection photo 1, 22 February 2023
  • Peninsula Three construction site, inspection photo 2, 22 February 2023
  • Peninsula Three construction site, inspection photo 3, 22 February 2023
  • Peninsula Three construction site, inspection photo 4, 22 February 2023

All 59 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Peninsula Three?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Peninsula Three handover date?
Construction of Peninsula Three is recorded as complete, with a registered completion date of June 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Peninsula Three?
Peninsula Three was 100% built at the site inspection on 27 November 2025. The site has been inspected 8 times since February 2023. The Land Department took 59 site photos at its inspections.
Is Peninsula Three delayed?
The register lists construction as complete.
Who is building Peninsula Three?
The registered developer is Select Global Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Peninsula Three?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.