Peninsula Four construction progress
The register lists Peninsula Four in Business Bay as complete, with a registered completion date of February 2026. Its last site inspection on record was in June 2026. The developer is Select Global Development.
100%
Built, at the site inspection of 24 June 2026
Construction complete
- Registered completion date
- February 2026
- Construction started
- October 2022
- First registered
- October 2022
- Developer
- Select Global Development
- Community
- Business Bay
- Units
- 1,063
- Escrow bank
- Emirates NBD
- Name in Arabic
- بينينسولا فور
- Project number
- 2461
- Site inspections
- 11
Schedule
The register lists Peninsula Four as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
24 June 2026
100%+4.4 pts
15 April 2026
96%+7.1 pts
4 December 2025
88%+11 pts
27 August 2025
77%+9.0 pts
24 June 2025
68%+18 pts
21 February 2025
50%+18 pts
25 October 2024
32%+17 pts
25 June 2024
15%+1.9 pts
29 April 2024
13%+7.4 pts
19 June 2023
5.9%+5.9 pts
Context
Business Bay has 43 projects under construction, 37% built on average.
Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Peninsula Four?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Peninsula Four handover date?
- Construction of Peninsula Four is recorded as complete, with a registered completion date of February 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Peninsula Four?
- Peninsula Four was 100% built at the site inspection on 24 June 2026. The site has been inspected 11 times since October 2022. The Land Department took 90 site photos at its inspections.
- Is Peninsula Four delayed?
- The register lists construction as complete.
- Who is building Peninsula Four?
- The registered developer is Select Global Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Peninsula Four?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nautica OneAlso by Select Global Development. 85%.
- Nautica TwoAlso by Select Global Development. 85%.
- Six Senses Residences Dubai MarinaAlso by Select Global Development. 27%.
- Artistry One ResidencesAlso by Select Global Development. 0%, Due February 2029.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





























.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)