Peninsula Five construction progress

The register lists Peninsula Five in Business Bay as complete, with a registered completion date of December 2024. Its last site inspection on record was in January 2025. The developer is Select Global Development.

100%

Built, at the site inspection of 13 January 2025

Construction complete

Registered completion date
December 2024
Construction started
January 2022
First registered
January 2022
Community
Business Bay
Units
383
Escrow bank
Emirates NBD
Name in Arabic
بينينسولا فايف
Project number
2344
Site inspections
5

Schedule

The register lists Peninsula Five as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 January 2025

100%+10 pts

  • Peninsula Five construction site, inspection photo 1, 13 January 2025
  • Peninsula Five construction site, inspection photo 2, 13 January 2025
  • Peninsula Five construction site, inspection photo 3, 13 January 2025
  • Peninsula Five construction site, inspection photo 4, 13 January 2025

4 July 2024

90%+61 pts

27 March 2024

29%

  • Peninsula Five construction site, inspection photo 1, 27 March 2024

24 August 2023

29%+25 pts

  • Peninsula Five construction site, inspection photo 1, 24 August 2023
  • Peninsula Five construction site, inspection photo 2, 24 August 2023
  • Peninsula Five construction site, inspection photo 3, 24 August 2023
  • Peninsula Five construction site, inspection photo 4, 24 August 2023

3 October 2022

4.1%

  • Peninsula Five construction site, inspection photo 1, 3 October 2022
  • Peninsula Five construction site, inspection photo 2, 3 October 2022
  • Peninsula Five construction site, inspection photo 3, 3 October 2022
  • Peninsula Five construction site, inspection photo 4, 3 October 2022

All 33 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Peninsula Five?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Peninsula Five handover date?
Construction of Peninsula Five is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Peninsula Five?
Peninsula Five was 100% built at the site inspection on 13 January 2025. The site has been inspected 5 times since October 2022. The Land Department took 33 site photos at its inspections.
Is Peninsula Five delayed?
The register lists construction as complete.
Who is building Peninsula Five?
The registered developer is Select Global Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Peninsula Five?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.