Bayz Tower construction progress

The register lists Bayz Tower in Business Bay as complete, with a registered completion date of May 2021. Its last site inspection on record was in May 2021. The developer is Danube Properties Development.

100%

Built, at the site inspection of 3 May 2021

Construction complete

Registered completion date
May 2021
Construction started
May 2017
First registered
May 2017
Community
Business Bay
Units
463
Escrow bank
United Bank Limited
Name in Arabic
بايز تاور
Project number
1889
Site inspections
13

Schedule

The register lists Bayz Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 May 2021

100%+20 pts

  • Bayz Tower construction site, inspection photo 1, 3 May 2021
  • Bayz Tower construction site, inspection photo 2, 3 May 2021
  • Bayz Tower construction site, inspection photo 3, 3 May 2021
  • Bayz Tower construction site, inspection photo 4, 3 May 2021

31 December 2020

80%+14 pts

  • Bayz Tower construction site, inspection photo 1, 31 December 2020
  • Bayz Tower construction site, inspection photo 2, 31 December 2020
  • Bayz Tower construction site, inspection photo 3, 31 December 2020
  • Bayz Tower construction site, inspection photo 4, 31 December 2020

10 September 2020

66%+12 pts

  • Bayz Tower construction site, inspection photo 1, 10 September 2020
  • Bayz Tower construction site, inspection photo 2, 10 September 2020
  • Bayz Tower construction site, inspection photo 3, 10 September 2020
  • Bayz Tower construction site, inspection photo 4, 10 September 2020

2 June 2020

54%+18 pts

  • Bayz Tower construction site, inspection photo 1, 2 June 2020
  • Bayz Tower construction site, inspection photo 2, 2 June 2020
  • Bayz Tower construction site, inspection photo 3, 2 June 2020
  • Bayz Tower construction site, inspection photo 4, 2 June 2020

27 January 2020

36%+8.5 pts

  • Bayz Tower construction site, inspection photo 1, 27 January 2020
  • Bayz Tower construction site, inspection photo 2, 27 January 2020
  • Bayz Tower construction site, inspection photo 3, 27 January 2020
  • Bayz Tower construction site, inspection photo 4, 27 January 2020

16 October 2019

27%+7.3 pts

  • Bayz Tower construction site, inspection photo 1, 16 October 2019
  • Bayz Tower construction site, inspection photo 2, 16 October 2019
  • Bayz Tower construction site, inspection photo 3, 16 October 2019
  • Bayz Tower construction site, inspection photo 4, 16 October 2019

3 July 2019

20%+8.9 pts

  • Bayz Tower construction site, inspection photo 1, 3 July 2019
  • Bayz Tower construction site, inspection photo 2, 3 July 2019
  • Bayz Tower construction site, inspection photo 3, 3 July 2019
  • Bayz Tower construction site, inspection photo 4, 3 July 2019

21 March 2019

11%+2.9 pts

  • Bayz Tower construction site, inspection photo 1, 21 March 2019
  • Bayz Tower construction site, inspection photo 2, 21 March 2019
  • Bayz Tower construction site, inspection photo 3, 21 March 2019
  • Bayz Tower construction site, inspection photo 4, 21 March 2019

24 December 2018

8.2%+3.0 pts

  • Bayz Tower construction site, inspection photo 1, 24 December 2018
  • Bayz Tower construction site, inspection photo 2, 24 December 2018
  • Bayz Tower construction site, inspection photo 3, 24 December 2018
  • Bayz Tower construction site, inspection photo 4, 24 December 2018

24 September 2018

5.2%+3.1 pts

  • Bayz Tower construction site, inspection photo 1, 24 September 2018
  • Bayz Tower construction site, inspection photo 2, 24 September 2018
  • Bayz Tower construction site, inspection photo 3, 24 September 2018
  • Bayz Tower construction site, inspection photo 4, 24 September 2018

All 123 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Bayz Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Bayz Tower handover date?
Construction of Bayz Tower is recorded as complete, with a registered completion date of May 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Bayz Tower?
Bayz Tower was 100% built at the site inspection on 3 May 2021. The site has been inspected 13 times since October 2017. The Land Department took 123 site photos at its inspections.
Is Bayz Tower delayed?
The register lists construction as complete.
Who is building Bayz Tower?
The registered developer is Danube Properties Development. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Bayz Tower?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.