Bayz Tower construction photos
123 photos from 13 site inspections, newest first. The percentage is how much of Bayz Tower was built on the day of each visit.
3 May 2021100% built
31 December 202080% built
10 September 202066% built
2 June 202054% built
27 January 202036% built
16 October 201927% built
3 July 201920% built
21 March 201911% built
24 December 20188.2% built
24 September 20185.2% built
19 June 20182.1% built
12 March 20180.7% built
30 October 20170% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.