360 Riverside Crescent construction progress
360 Riverside Crescent in Bukadra is 51% built at the Land Department inspection of September 2026. Developer Sobha.
51%
Built, at the Land Department site inspection of 16 September 2026
Schedule
Since November 2025 360 Riverside Crescent has added about 2.4 points a month. At that rate the site reaches 100% around June 2028. The Land Department has no completion date on record to compare it with.
Site inspections
16 September 2026
51%+7.8 pts
16 June 2026
43%+6.7 pts
26 March 2026
36%+9.1 pts
20 November 2025
27%+7.0 pts
9 May 2025
20%+9.7 pts
23 December 2024
10%+10 pts
14 May 2024
0%
Context
Bukadra has 21 projects under construction, 26% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in 360 Riverside Crescent?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will 360 Riverside Crescent be completed?
- The Land Department has no completion date on record for 360 Riverside Crescent yet.
- How much of 360 Riverside Crescent is built?
- 51%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 7 times since May 2024.
- Who is building 360 Riverside Crescent?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for 360 Riverside Crescent?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 37%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vistas HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- Claydon House By EllingtonNearby in Bukadra. 16%, Due December 2027.
- The Waterway By Prestige OneNearby in Bukadra. 15%, Due June 2027.
- Parkway By Prestige OneNearby in Bukadra. 11%, Due January 2028.
- Ayaan Heights INearby in Bukadra. 20%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.











.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)