360 Riverside Crescent construction progress

No completion date is registered for 360 Riverside Crescent in Bukadra yet. At the last site inspection, in September 2026, it was 51% built. The developer is Sobha.

51%

Built, at the site inspection of 16 September 2026

Finish at recent pace
June 2028
Construction started
May 2024
First registered
May 2024
Developer
Sobha
Community
Bukadra
Units
910
Escrow bank
Emirates NBD
Name in Arabic
ريفرسايد كريسنت 360
Project number
3079
Site inspections
7

Schedule

Since November 2025 360 Riverside Crescent has added about 2.4 points a month. At that rate the site reaches 100% around June 2028. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

16 September 2026

51%+7.8 pts

  • 360 Riverside Crescent construction site, inspection photo 1, 16 September 2026
  • 360 Riverside Crescent construction site, inspection photo 2, 16 September 2026
  • 360 Riverside Crescent construction site, inspection photo 3, 16 September 2026
  • 360 Riverside Crescent construction site, inspection photo 4, 16 September 2026

16 June 2026

43%+6.7 pts

  • 360 Riverside Crescent construction site, inspection photo 1, 16 June 2026
  • 360 Riverside Crescent construction site, inspection photo 2, 16 June 2026
  • 360 Riverside Crescent construction site, inspection photo 3, 16 June 2026
  • 360 Riverside Crescent construction site, inspection photo 4, 16 June 2026

26 March 2026

36%+9.1 pts

  • 360 Riverside Crescent construction site, inspection photo 1, 26 March 2026
  • 360 Riverside Crescent construction site, inspection photo 2, 26 March 2026
  • 360 Riverside Crescent construction site, inspection photo 3, 26 March 2026
  • 360 Riverside Crescent construction site, inspection photo 4, 26 March 2026

20 November 2025

27%+7.0 pts

  • 360 Riverside Crescent construction site, inspection photo 1, 20 November 2025
  • 360 Riverside Crescent construction site, inspection photo 2, 20 November 2025
  • 360 Riverside Crescent construction site, inspection photo 3, 20 November 2025
  • 360 Riverside Crescent construction site, inspection photo 4, 20 November 2025

9 May 2025

20%+9.7 pts

  • 360 Riverside Crescent construction site, inspection photo 1, 9 May 2025
  • 360 Riverside Crescent construction site, inspection photo 2, 9 May 2025
  • 360 Riverside Crescent construction site, inspection photo 3, 9 May 2025
  • 360 Riverside Crescent construction site, inspection photo 4, 9 May 2025

23 December 2024

10%+10 pts

  • 360 Riverside Crescent construction site, inspection photo 1, 23 December 2024
  • 360 Riverside Crescent construction site, inspection photo 2, 23 December 2024
  • 360 Riverside Crescent construction site, inspection photo 3, 23 December 2024
  • 360 Riverside Crescent construction site, inspection photo 4, 23 December 2024

14 May 2024

0%

  • 360 Riverside Crescent construction site, inspection photo 1, 14 May 2024
  • 360 Riverside Crescent construction site, inspection photo 2, 14 May 2024

All 56 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 27% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 360 Riverside Crescent?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 360 Riverside Crescent handover date?
No completion date is on record for 360 Riverside Crescent yet. Handover follows completion, so there is no date to give.
What is the latest construction update on 360 Riverside Crescent?
360 Riverside Crescent was 51% built at the site inspection on 16 September 2026. The site has been inspected 7 times since May 2024. The Land Department took 56 site photos at its inspections.
Who is building 360 Riverside Crescent?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for 360 Riverside Crescent?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.