Ayaan Heights I construction progress

The registered completion date for Ayaan Heights I in Bukadra is March 2028. At the last site inspection, in July 2026, it was 20% built. The developer is Digo Real Estate Development (Br Of Invest Group Overseas ).

20%

Built, at the site inspection of 8 July 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
May 2029
Construction started
October 2025
First registered
June 2025
Community
Bukadra
Units
130
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أيان هايتس 1
Project number
3610
Site inspections
4

Schedule

Between December 2025 and July 2026 the site added about 2.3 points a month. At that rate it would finish around May 2029, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 July 2026

20%+9.8 pts

  • Ayaan Heights I construction site, inspection photo 1, 8 July 2026
  • Ayaan Heights I construction site, inspection photo 2, 8 July 2026
  • Ayaan Heights I construction site, inspection photo 3, 8 July 2026
  • Ayaan Heights I construction site, inspection photo 4, 8 July 2026

2 April 2026

10%+6.3 pts

  • Ayaan Heights I construction site, inspection photo 1, 2 April 2026
  • Ayaan Heights I construction site, inspection photo 2, 2 April 2026
  • Ayaan Heights I construction site, inspection photo 3, 2 April 2026
  • Ayaan Heights I construction site, inspection photo 4, 2 April 2026

9 December 2025

4.2%+4.2 pts

  • Ayaan Heights I construction site, inspection photo 1, 9 December 2025
  • Ayaan Heights I construction site, inspection photo 2, 9 December 2025
  • Ayaan Heights I construction site, inspection photo 3, 9 December 2025
  • Ayaan Heights I construction site, inspection photo 4, 9 December 2025

20 March 2025

0%

  • Ayaan Heights I construction site, inspection photo 1, 20 March 2025
  • Ayaan Heights I construction site, inspection photo 2, 20 March 2025

All 24 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 27% built on average.

Digo Real Estate Development (Br Of Invest Group Overseas ) has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Ayaan Heights I?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ayaan Heights I handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ayaan Heights I?
Ayaan Heights I was 20% built at the site inspection on 8 July 2026. The site has been inspected 4 times since March 2025. The Land Department took 24 site photos at its inspections.
Is Ayaan Heights I delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Ayaan Heights I?
The registered developer is Digo Real Estate Development (Br Of Invest Group Overseas ). It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Ayaan Heights I?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.