Parkway By Prestige One construction progress

Parkway By Prestige One in Bukadra is 11% built at the Land Department inspection of August 2026. Developer Prestige The Parkway Real Estate Development. Completion registered for January 2028.

11%

Built, at the Land Department site inspection of 17 August 2026

Running behind its date

Completion date (Land Department)
January 2028
Finish at recent pace
March 2034
Construction started
February 2025
Registered with the Land Department
October 2024
Developer
Prestige The Parkway Real Estate Development
Community
Bukadra
Units
274
Escrow bank
Emirates NBD
Name in Arabic
باركواي باي برستيج ون
Land Department project number
3272
Land Department site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around March 2034, more than three months after the January 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 August 2026

11%+3.2 pts

  • Parkway By Prestige One construction site, Land Department inspection photo 1, 17 August 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 2, 17 August 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 3, 17 August 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 4, 17 August 2026

12 May 2026

7.7%+1.6 pts

  • Parkway By Prestige One construction site, Land Department inspection photo 1, 12 May 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 2, 12 May 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 3, 12 May 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 4, 12 May 2026

20 January 2026

6.0%+5.1 pts

  • Parkway By Prestige One construction site, Land Department inspection photo 1, 20 January 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 2, 20 January 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 3, 20 January 2026
  • Parkway By Prestige One construction site, Land Department inspection photo 4, 20 January 2026

9 October 2025

0.9%+0.7 pts

  • Parkway By Prestige One construction site, Land Department inspection photo 1, 9 October 2025
  • Parkway By Prestige One construction site, Land Department inspection photo 2, 9 October 2025
  • Parkway By Prestige One construction site, Land Department inspection photo 3, 9 October 2025
  • Parkway By Prestige One construction site, Land Department inspection photo 4, 9 October 2025

20 June 2025

0.2%+0.2 pts

  • Parkway By Prestige One construction site, Land Department inspection photo 1, 20 June 2025
  • Parkway By Prestige One construction site, Land Department inspection photo 2, 20 June 2025
  • Parkway By Prestige One construction site, Land Department inspection photo 3, 20 June 2025

4 September 2024

0%

  • Parkway By Prestige One construction site, Land Department inspection photo 1, 4 September 2024
  • Parkway By Prestige One construction site, Land Department inspection photo 2, 4 September 2024

All 25 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 26% built on average. Parkway By Prestige One is behind that average.

Own a unit in Parkway By Prestige One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Parkway By Prestige One be completed?
The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around March 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Parkway By Prestige One is built?
11%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 6 times since September 2024.
Is Parkway By Prestige One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Parkway By Prestige One?
The registered developer is Prestige The Parkway Real Estate Development.
Which bank holds the escrow account for Parkway By Prestige One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.