Parkway By Prestige One construction progress
Parkway By Prestige One in Bukadra is 11% built at the Land Department inspection of August 2026. Developer Prestige The Parkway Real Estate Development. Completion registered for January 2028.
11%
Built, at the Land Department site inspection of 17 August 2026
Running behind its date
- Completion date (Land Department)
- January 2028
- Finish at recent pace
- March 2034
- Construction started
- February 2025
- Registered with the Land Department
- October 2024
- Developer
- Prestige The Parkway Real Estate Development
- Community
- Bukadra
- Units
- 274
- Escrow bank
- Emirates NBD
- Name in Arabic
- باركواي باي برستيج ون
- Land Department project number
- 3272
- Land Department site inspections
- 6
Schedule
Between October 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around March 2034, more than three months after the January 2028 date registered with the Land Department.
Site inspections
17 August 2026
11%+3.2 pts
12 May 2026
7.7%+1.6 pts
20 January 2026
6.0%+5.1 pts
9 October 2025
0.9%+0.7 pts
20 June 2025
0.2%+0.2 pts
4 September 2024
0%
Context
Bukadra has 21 projects under construction, 26% built on average. Parkway By Prestige One is behind that average.
Own a unit in Parkway By Prestige One?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Parkway By Prestige One be completed?
- The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around March 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Parkway By Prestige One is built?
- 11%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 6 times since September 2024.
- Is Parkway By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
- Who is building Parkway By Prestige One?
- The registered developer is Prestige The Parkway Real Estate Development.
- Which bank holds the escrow account for Parkway By Prestige One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 330 Riverside CrescentNearby in Bukadra. 60%.
- Sobha EstatesNearby in Bukadra. 68%, Due December 2027.
- 310 Riverside CrescentNearby in Bukadra. 50%.
- 360 Riverside CrescentNearby in Bukadra. 51%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.