Parkway By Prestige One construction progress

The registered completion date for Parkway By Prestige One in Bukadra is January 2028. At the last site inspection, in August 2026, it was 11% built. The developer is Prestige The Parkway Real Estate Development.

11%

Built, at the site inspection of 17 August 2026

Running behind its date

Registered completion date
January 2028
Finish at recent pace
March 2034
Construction started
February 2025
First registered
October 2024
Developer
Prestige The Parkway Real Estate Development
Community
Bukadra
Units
274
Escrow bank
Emirates NBD
Name in Arabic
باركواي باي برستيج ون
Project number
3272
Site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around March 2034, more than three months after its registered date of January 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 August 2026

11%+3.2 pts

  • Parkway By Prestige One construction site, inspection photo 1, 17 August 2026
  • Parkway By Prestige One construction site, inspection photo 2, 17 August 2026
  • Parkway By Prestige One construction site, inspection photo 3, 17 August 2026
  • Parkway By Prestige One construction site, inspection photo 4, 17 August 2026

12 May 2026

7.7%+1.6 pts

  • Parkway By Prestige One construction site, inspection photo 1, 12 May 2026
  • Parkway By Prestige One construction site, inspection photo 2, 12 May 2026
  • Parkway By Prestige One construction site, inspection photo 3, 12 May 2026
  • Parkway By Prestige One construction site, inspection photo 4, 12 May 2026

20 January 2026

6.0%+5.1 pts

  • Parkway By Prestige One construction site, inspection photo 1, 20 January 2026
  • Parkway By Prestige One construction site, inspection photo 2, 20 January 2026
  • Parkway By Prestige One construction site, inspection photo 3, 20 January 2026
  • Parkway By Prestige One construction site, inspection photo 4, 20 January 2026

9 October 2025

0.9%+0.7 pts

  • Parkway By Prestige One construction site, inspection photo 1, 9 October 2025
  • Parkway By Prestige One construction site, inspection photo 2, 9 October 2025
  • Parkway By Prestige One construction site, inspection photo 3, 9 October 2025
  • Parkway By Prestige One construction site, inspection photo 4, 9 October 2025

20 June 2025

0.2%+0.2 pts

  • Parkway By Prestige One construction site, inspection photo 1, 20 June 2025
  • Parkway By Prestige One construction site, inspection photo 2, 20 June 2025
  • Parkway By Prestige One construction site, inspection photo 3, 20 June 2025

4 September 2024

0%

  • Parkway By Prestige One construction site, inspection photo 1, 4 September 2024
  • Parkway By Prestige One construction site, inspection photo 2, 4 September 2024

All 25 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 27% built on average.

Own a unit in Parkway By Prestige One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Parkway By Prestige One handover date?
The registered completion date is January 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Parkway By Prestige One?
Parkway By Prestige One was 11% built at the site inspection on 17 August 2026. The site has been inspected 6 times since September 2024. The Land Department took 25 site photos at its inspections.
Is Parkway By Prestige One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Parkway By Prestige One?
The registered developer is Prestige The Parkway Real Estate Development.
Which bank holds the escrow account for Parkway By Prestige One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.