The Waterway By Prestige One construction progress
The Waterway By Prestige One in Bukadra is 15% built at the Land Department inspection of August 2026. Developer Prestige The Waterway Real Estate Development. Completion registered for June 2027.
15%
Built, at the Land Department site inspection of 17 August 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- February 2032
- Construction started
- November 2024
- Registered with the Land Department
- September 2024
- Developer
- Prestige The Waterway Real Estate Development
- Community
- Bukadra
- Units
- 115
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا ووتر واي باي بريستسج وان
- Land Department project number
- 3198
- Land Department site inspections
- 6
Schedule
Between October 2025 and August 2026 the site added about 1.3 points a month. At that rate it would finish around February 2032, more than three months after the June 2027 date registered with the Land Department.
Site inspections
17 August 2026
15%+6.3 pts
12 May 2026
8.4%+3.3 pts
20 January 2026
5.1%+3.7 pts
8 October 2025
1.4%+0.8 pts
20 June 2025
0.5%+0.5 pts
23 July 2024
0%
Context
Bukadra has 21 projects under construction, 26% built on average.
Own a unit in The Waterway By Prestige One?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Waterway By Prestige One be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around February 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Waterway By Prestige One is built?
- 15%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 6 times since July 2024.
- Is The Waterway By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building The Waterway By Prestige One?
- The registered developer is Prestige The Waterway Real Estate Development.
- Which bank holds the escrow account for The Waterway By Prestige One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 330 Riverside CrescentNearby in Bukadra. 60%.
- Sobha EstatesNearby in Bukadra. 68%, Due December 2027.
- 310 Riverside CrescentNearby in Bukadra. 50%.
- 360 Riverside CrescentNearby in Bukadra. 51%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)