The Waterway By Prestige One construction progress

The Waterway By Prestige One in Bukadra is 15% built at the Land Department inspection of August 2026. Developer Prestige The Waterway Real Estate Development. Completion registered for June 2027.

15%

Built, at the Land Department site inspection of 17 August 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
February 2032
Construction started
November 2024
Registered with the Land Department
September 2024
Developer
Prestige The Waterway Real Estate Development
Community
Bukadra
Units
115
Escrow bank
Emirates NBD
Name in Arabic
ذا ووتر واي باي بريستسج وان
Land Department project number
3198
Land Department site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 1.3 points a month. At that rate it would finish around February 2032, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 August 2026

15%+6.3 pts

  • The Waterway By Prestige One construction site, Land Department inspection photo 1, 17 August 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 2, 17 August 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 3, 17 August 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 4, 17 August 2026

12 May 2026

8.4%+3.3 pts

  • The Waterway By Prestige One construction site, Land Department inspection photo 1, 12 May 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 2, 12 May 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 3, 12 May 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 4, 12 May 2026

20 January 2026

5.1%+3.7 pts

  • The Waterway By Prestige One construction site, Land Department inspection photo 1, 20 January 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 2, 20 January 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 3, 20 January 2026
  • The Waterway By Prestige One construction site, Land Department inspection photo 4, 20 January 2026

8 October 2025

1.4%+0.8 pts

  • The Waterway By Prestige One construction site, Land Department inspection photo 1, 8 October 2025
  • The Waterway By Prestige One construction site, Land Department inspection photo 2, 8 October 2025
  • The Waterway By Prestige One construction site, Land Department inspection photo 3, 8 October 2025

20 June 2025

0.5%+0.5 pts

  • The Waterway By Prestige One construction site, Land Department inspection photo 1, 20 June 2025
  • The Waterway By Prestige One construction site, Land Department inspection photo 2, 20 June 2025
  • The Waterway By Prestige One construction site, Land Department inspection photo 3, 20 June 2025
  • The Waterway By Prestige One construction site, Land Department inspection photo 4, 20 June 2025

23 July 2024

0%

  • The Waterway By Prestige One construction site, Land Department inspection photo 1, 23 July 2024
  • The Waterway By Prestige One construction site, Land Department inspection photo 2, 23 July 2024
  • The Waterway By Prestige One construction site, Land Department inspection photo 3, 23 July 2024

All 27 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 26% built on average.

Own a unit in The Waterway By Prestige One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Waterway By Prestige One be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around February 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Waterway By Prestige One is built?
15%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 6 times since July 2024.
Is The Waterway By Prestige One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building The Waterway By Prestige One?
The registered developer is Prestige The Waterway Real Estate Development.
Which bank holds the escrow account for The Waterway By Prestige One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.