360 Riverside Crescent construction photos
56 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of 360 Riverside Crescent was built on the day of each visit.
16 September 202651% built
16 June 202643% built
26 March 202636% built
20 November 202527% built
9 May 202520% built
23 December 202410% built
14 May 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.