Claydon House By Ellington construction progress

Claydon House By Ellington in Bukadra is 16% built at the Land Department inspection of August 2026. Developer E L P D Developers. Completion registered for December 2027.

16%

Built, at the Land Department site inspection of 6 August 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
October 2033
Construction started
May 2024
Registered with the Land Department
November 2024
Developer
E L P D Developers
Community
Bukadra
Units
415
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كلايدون هاوس من إلينغتون
Land Department project number
3098
Land Department site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around October 2033, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 August 2026

16%+6.0 pts

  • Claydon House By Ellington construction site, Land Department inspection photo 1, 6 August 2026
  • Claydon House By Ellington construction site, Land Department inspection photo 2, 6 August 2026
  • Claydon House By Ellington construction site, Land Department inspection photo 3, 6 August 2026
  • Claydon House By Ellington construction site, Land Department inspection photo 4, 6 August 2026

13 April 2026

9.7%+2.5 pts

  • Claydon House By Ellington construction site, Land Department inspection photo 1, 13 April 2026
  • Claydon House By Ellington construction site, Land Department inspection photo 2, 13 April 2026
  • Claydon House By Ellington construction site, Land Department inspection photo 3, 13 April 2026
  • Claydon House By Ellington construction site, Land Department inspection photo 4, 13 April 2026

13 November 2025

7.2%+3.1 pts

  • Claydon House By Ellington construction site, Land Department inspection photo 1, 13 November 2025
  • Claydon House By Ellington construction site, Land Department inspection photo 2, 13 November 2025

30 June 2025

4.1%+4.1 pts

  • Claydon House By Ellington construction site, Land Department inspection photo 1, 30 June 2025
  • Claydon House By Ellington construction site, Land Department inspection photo 2, 30 June 2025
  • Claydon House By Ellington construction site, Land Department inspection photo 3, 30 June 2025
  • Claydon House By Ellington construction site, Land Department inspection photo 4, 30 June 2025

23 May 2024

0%

  • Claydon House By Ellington construction site, Land Department inspection photo 1, 23 May 2024
  • Claydon House By Ellington construction site, Land Department inspection photo 2, 23 May 2024

All 19 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 26% built on average.

Own a unit in Claydon House By Ellington?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Claydon House By Ellington be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Claydon House By Ellington is built?
16%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 5 times since May 2024.
Is Claydon House By Ellington delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Claydon House By Ellington?
The registered developer is E L P D Developers.
Which bank holds the escrow account for Claydon House By Ellington?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.