Claydon House By Ellington construction progress
Claydon House By Ellington in Bukadra is 16% built at the Land Department inspection of August 2026. Developer E L P D Developers. Completion registered for December 2027.
16%
Built, at the Land Department site inspection of 6 August 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- October 2033
- Construction started
- May 2024
- Registered with the Land Department
- November 2024
- Developer
- E L P D Developers
- Community
- Bukadra
- Units
- 415
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- كلايدون هاوس من إلينغتون
- Land Department project number
- 3098
- Land Department site inspections
- 5
Schedule
Between November 2025 and August 2026 the site added about 1.0 points a month. At that rate it would finish around October 2033, more than three months after the December 2027 date registered with the Land Department.
Site inspections
6 August 2026
16%+6.0 pts
13 April 2026
9.7%+2.5 pts
13 November 2025
7.2%+3.1 pts
30 June 2025
4.1%+4.1 pts
23 May 2024
0%
Context
Bukadra has 21 projects under construction, 26% built on average.
Own a unit in Claydon House By Ellington?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Claydon House By Ellington be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Claydon House By Ellington is built?
- 16%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 5 times since May 2024.
- Is Claydon House By Ellington delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Claydon House By Ellington?
- The registered developer is E L P D Developers.
- Which bank holds the escrow account for Claydon House By Ellington?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 330 Riverside CrescentNearby in Bukadra. 60%.
- Sobha EstatesNearby in Bukadra. 68%, Due December 2027.
- 310 Riverside CrescentNearby in Bukadra. 50%.
- 360 Riverside CrescentNearby in Bukadra. 51%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.