330 Riverside Crescent construction photos
52 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of 330 Riverside Crescent was built on the day of each visit.
9 July 202660% built
18 March 202649% built
10 November 202538% built
28 July 202531% built
16 April 202523% built
7 January 202520% built
17 September 202416% built
23 May 20247.7% built
12 October 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.