320 Riverside Crescent construction progress

No completion date is registered for 320 Riverside Crescent in Bukadra yet. At the last site inspection, in August 2026, it was 57% built. The developer is Sobha.

57%

Built, at the site inspection of 24 August 2026

Finish at recent pace
March 2028
Construction started
May 2024
First registered
May 2024
Developer
Sobha
Community
Bukadra
Units
638
Escrow bank
Emirates NBD
Name in Arabic
ريفرسايد كريسنت 320
Project number
3088
Site inspections
8

Schedule

Since September 2025 320 Riverside Crescent has added about 2.3 points a month. At that rate the site reaches 100% around March 2028. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

24 August 2026

57%+6.5 pts

  • 320 Riverside Crescent construction site, inspection photo 1, 24 August 2026
  • 320 Riverside Crescent construction site, inspection photo 2, 24 August 2026
  • 320 Riverside Crescent construction site, inspection photo 3, 24 August 2026
  • 320 Riverside Crescent construction site, inspection photo 4, 24 August 2026

22 May 2026

50%+13 pts

  • 320 Riverside Crescent construction site, inspection photo 1, 22 May 2026
  • 320 Riverside Crescent construction site, inspection photo 2, 22 May 2026
  • 320 Riverside Crescent construction site, inspection photo 3, 22 May 2026
  • 320 Riverside Crescent construction site, inspection photo 4, 22 May 2026

9 February 2026

37%+6.2 pts

  • 320 Riverside Crescent construction site, inspection photo 1, 9 February 2026
  • 320 Riverside Crescent construction site, inspection photo 2, 9 February 2026
  • 320 Riverside Crescent construction site, inspection photo 3, 9 February 2026
  • 320 Riverside Crescent construction site, inspection photo 4, 9 February 2026

15 September 2025

31%+11 pts

  • 320 Riverside Crescent construction site, inspection photo 1, 15 September 2025
  • 320 Riverside Crescent construction site, inspection photo 2, 15 September 2025
  • 320 Riverside Crescent construction site, inspection photo 3, 15 September 2025
  • 320 Riverside Crescent construction site, inspection photo 4, 15 September 2025

9 May 2025

20%+3.1 pts

  • 320 Riverside Crescent construction site, inspection photo 1, 9 May 2025
  • 320 Riverside Crescent construction site, inspection photo 2, 9 May 2025
  • 320 Riverside Crescent construction site, inspection photo 3, 9 May 2025
  • 320 Riverside Crescent construction site, inspection photo 4, 9 May 2025

11 February 2025

17%+3.7 pts

  • 320 Riverside Crescent construction site, inspection photo 1, 11 February 2025
  • 320 Riverside Crescent construction site, inspection photo 2, 11 February 2025
  • 320 Riverside Crescent construction site, inspection photo 3, 11 February 2025
  • 320 Riverside Crescent construction site, inspection photo 4, 11 February 2025

5 November 2024

13%+13 pts

  • 320 Riverside Crescent construction site, inspection photo 1, 5 November 2024
  • 320 Riverside Crescent construction site, inspection photo 2, 5 November 2024
  • 320 Riverside Crescent construction site, inspection photo 3, 5 November 2024
  • 320 Riverside Crescent construction site, inspection photo 4, 5 November 2024

7 May 2024

0%

  • 320 Riverside Crescent construction site, inspection photo 1, 7 May 2024
  • 320 Riverside Crescent construction site, inspection photo 2, 7 May 2024
  • 320 Riverside Crescent construction site, inspection photo 3, 7 May 2024

All 60 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 27% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 320 Riverside Crescent?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 320 Riverside Crescent handover date?
No completion date is on record for 320 Riverside Crescent yet. Handover follows completion, so there is no date to give.
What is the latest construction update on 320 Riverside Crescent?
320 Riverside Crescent was 57% built at the site inspection on 24 August 2026. The site has been inspected 8 times since May 2024. The Land Department took 60 site photos at its inspections.
Who is building 320 Riverside Crescent?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for 320 Riverside Crescent?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.